Details
The MHP plant Ererte has a capacity of 33 kW and is planned to be inaugurated in September 2011. A total of approximately 200 households will be connected to the plant. The maximum number of potentially connectable households is 700.
► Click here for more information.
- Start of Construction: August 2009
- Date of Commissioning: -
- Ownership: Robot Electric Users Cooperative/community based cooperative society
- Tariff Structure: Flat rate/monthly based per appliance
- Technical Specification:
- Canal: Lined stone masonry having a length of 53m
- Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured
- Turbine: T-15 cross flow turbine /Manufactured locally
- Generator: MARELLI-Brushless Synchronous,1500 rpm, 42 kVA, 33.6 kW, 50 Hz, Efficiency - 89%, 380/440 V(adjustable), 3 phase series STAR
- Grid: Low Voltage distribution with ABC cable and Wooden pole (2.76 km)
Pictures
Further Information
- Hydro Portal on energypedia
- Ethiopia Energy Situation
- Micro Hydro Power (MHP) - Ethiopia, Gobecho I
- Micro Hydro Power (MHP) - Ethiopia, Gobecho II
- Micro Hydro Power (MHP) - Ethiopia, Hagara Sodicha