Knowledge fuels change - Support energypedia!
For over 10 years, energypedia has been connecting energy experts around the world — helping them share knowledge, learn from each other, and accelerate the global energy transition.
Today, we ask for your support to keep this platform free and accessible to all.
Even a small contribution makes a big difference! If just 10–20% of our 60,000+ monthly visitors donated the equivalent of a cup of coffee — €5 — Energypedia would be fully funded for a whole year.
Is the knowledge you’ve gained through Energypedia this year worth €5 or more?
Your donation keeps the platform running, helps us create new knowledge products, and contributes directly to achieving SDG 7.
Thank you for your support, your donation, big or small, truly matters!
Lom Pangar Hydropower Project - Economic and Financial Analysis
Lom Pangar Hydropower Project - Economic and Financial Analysis
| Title of Document | Lom Pangar Hydropower Project - Economic and Financial Analysis |
| Abstract | The project development objective is to increase hydropower generation capacity and reduce seasonal variability of water flow in the Sanaga River and to increase access to electricity. The document includes an example of economic and financial analysis: The economic analysis deals with demand forecast, demand scenarios and sensitivities to parameters; The financial analysis deals with the financial viability of the Lom Pangar dam and of the Lom Pangar power plant and with the financial situation of AES-SONEL and of the Electricity Development Corporation (EDC). |
| File Download | |
| Original Source | World Bank |
| Year | 2012 |
| Region/Country | Africa - Cameroon |
| Language(s) | English |
| Document Type | Project Financing- Examples of Economic & Financial Analysis |
| Technology | Hydro |
| Connection Type |