Back to the Hydropower Sites Database
General Information
Country:
|
Ethiopia
|
City/Town:
|
Amhara
|
Coordinates (Powerhouse):
|
13° 20' 57.12" N, 38° 44' 25.76" E
|
Year of Commission:
|
2009
|
Basin Name:
|
Tekeze River (a tributary of Atbarah River which is a tributary of the Nile)
|
Stream Name:
|
|
Developer:
|
|
Operator:
|
Ethiopian national grid at Mekele
|
Project Status:
|
Completed
|
Any other uses of the water source:
|
|
Contact:
|
|
Comment:
|
|
Link to Photos:
|
|
Technical Information
Power: (kW)
|
300.000
|
Energy (kWh/a):
|
981.000.000
|
Capacity Factor (%):
|
37
|
Penstock Diameter (mm):
|
|
Penstock Length (m):
|
|
Penstock Material (m³/s):
|
|
Maximum Flow of the Penstock (m³/s):
|
119
|
Minimum Flow of the Stream (m³/s):
|
|
Head (m):
|
155
|
Turbine Type:
|
Fracis turbines
|
Turbine Manufacturer:
|
Dongfang China
|
Generator Type:
|
|
Generator Capacity (kW):
|
|
Generator Manufacturer:
|
Dongfang China
|
Comment:
|
|
Mini/Island Grid Information
Mini Grid:
|
No
|
Load Control Information:
|
|
Connection Type:
|
|
Public Lighting:
|
|
Length of Transmission Line (m):
|
105000
|
Voltage (v):
|
230000
|
Transmission Conductor (type) :
|
|
Diameter of Conductor (mm²):
|
|
Transformer Rating (kVA):
|
|
Link to Grid:
|
|
S.W.E.R:
|
|
Operational Period (Xdays/year):
|
|
Comment:
|
|
Dam Information
Dam Type:
|
Dam on river with reservoir
|
Dam Construction Material:
|
Concrete Arch Dam
|
Dam Height [m]:
|
188
|
Length of Dam [m]:
|
420
|
Storage Volume of Reservoir (m³):
|
9310000000
|
Flood Storage of Reservoir:
|
|
Channel Material:
|
|
Comment:
|
|
Economic Information
Cost (€):
|
364,999,999
|
Donor/Financier & Percentage:
|
|
Tariff Levels:
|
|
Connected Households:
|
|
Connection Cost (€):
|
|
Cost to be Covered by Households (%):
|
|
Comment:
|
Project Financed By: China Exim Bank ($50 million)
|
Link to Cost Breakdown:
|
|