Knowledge fuels change - Support energypedia!
For over 10 years, energypedia has been connecting energy experts around the world — helping them share knowledge, learn from each other, and accelerate the global energy transition.
Today, we ask for your support to keep this platform free and accessible to all.
Even a small contribution makes a big difference! If just 10–20% of our 60,000+ monthly visitors donated the equivalent of a cup of coffee — €5 — Energypedia would be fully funded for a whole year.
Is the knowledge you’ve gained through Energypedia this year worth €5 or more?
Your donation keeps the platform running, helps us create new knowledge products, and contributes directly to achieving SDG 7.
Thank you for your support, your donation, big or small, truly matters!
Checklist for the Planning of a Biogas Plant
Overview
The following table gives an overview of all the steps required to build a biogas unit.
The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.
Step-by-Step Planning Checklist for Biogas Plants
| Customer |
Contractor |
|---|---|
| organizes advertisement, awareness creation | |
| hears about biogas, develops interest, get's in contact with the contractor |
|
| gives first overview over costs | |
| writes letter to the customer | |
| writes a request | |
| starts file | |
| makes a side visit, including: discussion and calculations | |
| makes a quantity survey, | |
| does object planning | |
| writes invoice explains warranty performances | |
| makes first payment (50%) | organizes a customer and constructor sign contract |
| hands over a list of building material to be delivered by the customer | |
| prepares the material he agreed to deliver | |
| organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping. | |
| starts to fill the plant second payment (50%) |
|
| finishes piping installation of gas consumption accessories | |
| discusses handing over | |
| makes an agreement on co-operation regarding fertiliser utilisation | |
| makes a follow up on fertiliser utilisation | |
| does customer monitoring | |
| conducts technical and agricultural service visits |