Difference between revisions of "Micro Hydro Power (MHP) - Ethiopia, Ererte"
From energypedia
***** (***** | *****) m |
***** (***** | *****) m |
||
Line 1: | Line 1: | ||
− | '''Location of the site''': | + | '''Location of the site''': |
− | *<u>Country</u>: Ethiopia | + | *<u>Country</u>: Ethiopia |
− | *<u>District</u>: Bona | + | *<u>District</u>: Bona |
− | *<u>Kebele</u>: Beshiro Gute | + | *<u>Kebele</u>: Beshiro Gute |
− | *<u>River</u>: Ererte | + | *<u>River</u>: Ererte |
*[[GPS coordinates - MHP sites EnDev|<u>GPS coordinate</u>]]<u>:</u> 6º33’26.8’’N 38º40’8.4’’ E | *[[GPS coordinates - MHP sites EnDev|<u>GPS coordinate</u>]]<u>:</u> 6º33’26.8’’N 38º40’8.4’’ E | ||
− | |||
− | |||
− | + | The MHP plant Ererte has a capacity of 33 kW and is planned to be inaugurated in September 2011. A total of approximately 200 households will be connected to the plant. The maximum number of potentially connectable households is 700. | |
− | + | Click [[:file:Factsheet ererti.pdf|here]] for more information. | |
− | ''' | + | <br/>'''Start of Construction: '''August 2009 |
− | + | '''Date of Commissioning:''' | |
− | |||
− | |||
− | + | '''Ownership:''' Robot Electric Users Cooperative/community based cooperative society | |
− | ''' | + | '''Tariff Structure:''' Flat rate/monthly based per appliance |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | {| | + | '''Technical Specification:''' |
+ | |||
+ | *Canal: Lined stone masonry having a length of 53m | ||
+ | *Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured | ||
+ | *Turbine: T-15 cross flow turbine /Manufactured locally | ||
+ | *Generator: MARELLI-Brushless Synchronous,1500 rpm, 42 kVA, 33.6 kW, 50 Hz, Efficiency - 89%, 380/440 V(adjustable), 3 phase series STAR | ||
+ | *Grid: Low Voltage distribution with ABC cable and Wooden pole (2.76 km) | ||
+ | |||
+ | |||
+ | |||
+ | {| class="FCK__ShowTableBorders" width="100%" border="0" cellpadding="1" cellspacing="1" | ||
|- | |- | ||
− | | [[ | + | | [[File:Ererti Fall.JPG|left|370px|Ererti Fall.JPG]] |
− | | [[ | + | | [[File:Ererti MHP site.JPG|left|370px|Ererti MHP site.JPG]] |
|- | |- | ||
− | | Ererte waterfall<br> | + | | Ererte waterfall<br/> |
− | | Ererte MHP site<br> | + | | Ererte MHP site<br/> |
|- | |- | ||
− | | [[ | + | | [[File:Ererti MHP weir ,Intake and canal.JPG|left|370px|Ererti MHP weir ,Intake and canal.JPG]] |
− | | [[ | + | | [[File:Locally Manufactured T-15 Turbine.JPG|left|370px|Locally Manufactured T-15 Turbine.JPG]] |
|- | |- | ||
− | | Ererte intake and canal<br> | + | | Ererte intake and canal<br/> |
− | | Locally Manufactured T-15 Turbine<br> | + | | Locally Manufactured T-15 Turbine<br/> |
|} | |} | ||
− | | + | |
− | + | [[Category:Ethiopia]] |
Revision as of 15:30, 30 August 2011
Location of the site:
- Country: Ethiopia
- District: Bona
- Kebele: Beshiro Gute
- River: Ererte
- GPS coordinate: 6º33’26.8’’N 38º40’8.4’’ E
The MHP plant Ererte has a capacity of 33 kW and is planned to be inaugurated in September 2011. A total of approximately 200 households will be connected to the plant. The maximum number of potentially connectable households is 700.
Click here for more information.
Start of Construction: August 2009
Date of Commissioning:
Ownership: Robot Electric Users Cooperative/community based cooperative society
Tariff Structure: Flat rate/monthly based per appliance
Technical Specification:
- Canal: Lined stone masonry having a length of 53m
- Penstock: Mild stell having a diameter of 400mm and a length of 42m/locally manufactured
- Turbine: T-15 cross flow turbine /Manufactured locally
- Generator: MARELLI-Brushless Synchronous,1500 rpm, 42 kVA, 33.6 kW, 50 Hz, Efficiency - 89%, 380/440 V(adjustable), 3 phase series STAR
- Grid: Low Voltage distribution with ABC cable and Wooden pole (2.76 km)
Ererte waterfall |
Ererte MHP site |
Ererte intake and canal |
Locally Manufactured T-15 Turbine |