Senegal Energy Situation

From energypedia
Revision as of 13:30, 24 June 2009 by ***** (***** | *****)


Energy situation especially in rural areas

Energy demand and supply in the household sector

The Senegalese energy sector is relatively small. The total final energy consumption in 2006 was about 2,3 Million TOE or 0.2 TOE per habitant, half of the all-africa average (0.45 TOE). The sector is dominated by the use of biomass (45 % of end energy-use) and oil products (44 %). Electricity and coal account only for 7 % and 4 % respectively. The household sector is responsible for 54% of the total energy consumption. Within this sector firewood (58 %) and charcoal (26 %) are by far the most important uses of energy, followed by LPG (11 %), Electricity (4 %) and lampoil (1 %)

Senegal´s energy consumption 2000-2006 subdivided into sectors

The figure on the right shows the development of the energy consumption in the sectors household, transport and industry.

Biomass
A big part of urban house-holds still cooks with wood and charcoal. The use of biomass is one of the key factors responsible for the depletion of the country's forest stocks. In the medium term deforestation will create bottle-necks in the supply of cooking energy, particularly for the poorest households.

Demand for charcoal derived from Senegalese forests is also likely to increase since there will be a phase-out of subsidies for butane gas in reaction to pressure from the West African Monetary Union, most likely prompting poorer households to return to their traditional fuel usage patterns. These traditional ways of cooking are generally characterised by very poor efficiency.

Some key figures:

  • 40,000 ha of forest are lost every year (to chopping for firewood, forest fires, desertification)
  • the price of traditional fuels (firewood, charcoal) has more than doubled in the last 10 years
  • an estimated 5,400 people annually die from diseases caused by indoor air pollution
  • 45 % of Senegal’s primary energy demand are covered by firewood (31 % directly as firewood and 14 % as charcoal)

The Senegalese government has recently published several policy orientations, thus beginning to address these extremely urgent issues.

Electricity

Since the year 2000 the electricity production is increasing annually by 7.2 % and was about 2400 GWh in 2006. Thereof 3,6 GWh are produced decentralized with PV application. In 2006 the households consumed 1438 GWh or 144 kWh per person. But as the demand for electricity grows faster than the supply Senegal has to deal with serious problems. This causes the scheduled or unscheduled outage of whole districts.

The electrification rate is relatively high: in urban areas is reaches 75 % and nationwide it´s around 45 % On the other hand, in 2008 only about 17 % of rural households have access to electricity. Recently, the government set the target of rural electrification to 50 % coverage by 2012. The goal seems very ambitious and explains the high ranking of rural electrification on the political agenda.

Rural Electrification

Senegal consist mostly of villages classified as small rural localities with less than 500 inhabitants (84%). Such villages accounted for 46% of the rural population in 2003. These communities are of less interest for private investors due to high cost of investment and relative low revenues.

The Senegalese government developed a concessionaire-model to electrify rural areas. The Rural Electrification Authority is responsible for its implementation (see Public Institutions and Actors). The model works as follows:

It was decided to divide the whole of Senegal into concession zones (12 concessions remain after a consolidation). International donors and the Senegalese government provide large amounts of money to supply the concessionaires with sufficient funds for their rural electrification activities. The donors involved are the World Bank, the German development bank KfW (1 concession) and the African Development Fund. The government provides up to 70 % of funds required for investment and engineering. The concessionaire is charged with 20 % and the users with 10 %. End users will be charged with cost covering tariffs. All donors have dedicated a share of their funds (ca. 15 %) for the installation of renewable energy systems.

The first concession was awarded in 2008. Within the concessions municipalities can apply for ERIL loans (Electrification Rurale d’Initiative Locale – rural electrification through local initiatives) to imple-ment electrification projects themselves. In ERILs, the same rules apply for subsidies as in the concessions (70 %/ 20 %/ 10 %). For all ERILs an application has to be prepared and submitted. Then, ASER and the respective concessionaire have to approve the project.

The concessionaires will start their rural electrification activities soon, but they will only reach a small part of the rural population. Following ASER's current strategy, almost all villages that are not located in vicinity of medium tension power supply lines will not be supplied with electricity within the next 10 to 15 years. In the concession zones of KfW in the Peanut Basin and the Casamance, for example, about 1 million people in 2,600 villages will not be connected to the grid.

Although in principle the two concession models of ASER (large-scale concessions, PPER, and concessions based on local initiative, ERIL), in conjunction with the tariffs set by the regulatory authority, ensure profitability of operators and thus continued maintenance (and hence sustainability), this was not yet proven in practice due to the small number of projects implemented and various delays in the administrative procedures.

Barriers to rural electrification are, among others, low purchasing power of the consumers (implying a need for subsidies if a broad range of people is to be targeted), the small number of qualified enterprises intervening on the rural market, and the incongruity of rural electrification funds and demand. In addition, administrative processes in the rural electrification agency ASER are lengthy and intransparent to potential operators (necessity for capacity building of ASER staff).

Institutional set up and actors in the energy sector

Public institutions and Actors

In 1997 Senegal began a reorganisation of its electricity sector following recommendations by the World Bank. It was decided to privatise the public utility SENELEC, to found the "Agence Sénégalaise d’Electrification Rurale" (ASER – Senegalese Authority for Rural Electrification) and to put in place the "Commission de Régulation du Secteur de l’Electricité" (CRSE – Regulation Commission for the power sector).

The Ministry of Energy and Biofuels (Ministère de l’Energie et des biocarburants) as the lead agency is in charge of formulating, coordinating, and setting overall objectives, policies, strategies, and general directives for the entire energy sector. Furthermore it is authorized to issue directives to SENELEC. The CRSE is responsible for the distribution and monitoring of concession and licences, for the market control (control of competition) and it fixes the end-user prices for electricity. ASER is the governmental agency which is charged with the task of rural electrification as well as the implementation of the concessions and the ERIL, while the urban electricity supply remained within the responsibility of SENELEC. ASER is the most important partner for rural development.

Electricity generation, transmission and distribution

'Power 'Generation:  Senegal’s total installed capacity is 634.9 MW, but in 2008 only 548.8 MW were used. Of these 512.1 MW are connected to the national grid. SENELEC owns power stations with nearly 60 % of the total production capacity while 218.3 MW are private US-owned by GTI-Dakar and ESKOM-Manantali.

The biggest part are 'generated' by diesel plants, but there are also gas-, steam- and gas-steam power plants. Senegal uses 60 MW of the 200 MW Manantali hydroelectric power plant at the border with Mali. This results into a strong dependency of the power price on the world market oil-price and the local Diesel price in both - national grid as well as in mini-grids.

Transmission: There are two grid-systems: the national grid at 90kV (327.5 km) and the supranational grid at 225 kV (945 km). Both are operated by SENELEC.The grid only supplies urban areas around Dakar, Thies, St. Louis and Kaolack/Fatick with electricity. But there´re several isolated networks in order to power some remote areas.

Distribution: All distribution activities are carried out by SENELEC.

Non governmental service providers for rural areas in the field of energy

Projects implementing NGOs


Commercial service provider

During the 1990s, Senegalese companies sold about 2,000 PV systems per year, but the reorganisation of the electricity sector had a negative impact of the nascent Senegalese market for solar energy systems. Only 7 out of 18 solar companies survived the reform. However, 6 new companies have entered the market since 1998, raising the number of solar energy providers to 13. The companies are mainly involved in installation and service for donor-funded systems while the market for unsubsidised systems is very small.

Micro Finance Institutions

Government
The ministry in charge of micro-finance ist the "Ministére de la Famille,de la Solidarité Nationale, de la Sécurité Alimentaire, de l'Entreprenariat Féminin, de la Micro Finance et de la Petite Enfance".

Senegal Ecovillage Microfinance Fund
The SEM Fund, or the Senegal Ecovillage Microfinance Fund, is a nonprofit organisation dedicated to alleviating poverty by providing affordable business loans aimed at strengthening the business skills and livelihoods of highly motivated microentrepreneurs that lack access to the commercial banking system.

Policy framework

Poverty reduction strategy and Energy policy

Senegegal´s Poverty Reduction Strategy Paper (PRSP) pushes the poverty reduction agenda forward so as to meet the objective of raising economic growth to about 7 percent per year necessary to halve poverty by 2015, in line with the targets set out in the New Partnership for Africa's Development (NEPAD) and the Millennium Development Goals (MDGs).

The PRSP names are ten overall objectives for the development of the energy sector:

  1. develop the institutional framework and production capacity for energy
  2. promote the engine o f productive activities
  3. involve private operators, village associations and local authorities in the development of energy infrastructures and services;
  4. ensure the financing of activities aimed at developing the energy sector
  5. diversify energy sources and technologies
  6. promote the control of energy and renewable energy sources
  7. create an investment program for access to energy services aimed at economic and human development
  8. provide better and safer public access to domestic fuels
  9. enhance access to energy services in rural and suburban areas so as to facilitate the working of basic infrastructures (schools, healthcare facilities, conservation infrastructures, etc.)
  10. improve access to oil and gas.

Key problems hampering access to modern energy services in rural areas

Obstacles for grid based rural electrification

  • Even though the concessionaires will soon start their rural electrification activities, they will only reach a small part of the rural population. Following ASER's current strategy, almost all villages that are not located in vicinity of medium tension power supply lines will not be supplied with electricity within the next 10 to 15 years. In the concession zones of KfW (German implementing agency for financial cooperation) in the Peanut Basin and the Casamance, for example, about 1 million people in 2,600 villages will not be connected to the grid.
  • administrative processes in the rural electrification agency ASER are lengthy and intransparent to potential operators (necessity for capacity building of ASER staff).
  • Although in principle the two concession models of ASER (large-scale concessions, PPER, and conces-sions based on local initiative, ERIL), in conjunction with the tariffs set by the regulatory authority, ensure profitability of operators and thus continued maintenance (and hence sustainability), this was not yet proven in practice due to the small number of projects implemented and various delays in the ad-ministrative procedures.

Obstacles for off grid energy technologies and services

  • low purchasing power of the consumers (implying a need for subsidies if a broad range of people is to be targeted
  • small number of qualified enterprises intervening on the rural market
  • incongruity of rural electrification funds and demand