Difference between revisions of "Hydro - Environmental Impact Assessment (EIA)"
***** (***** | *****) m |
***** (***** | *****) m |
||
Line 1: | Line 1: | ||
− | + | = Introduction<br/> = | |
An '''environmental impact assessment (EIA)''' is an assessment of the possible impact - positive or negative - that a proposed project may have on the environment, considering natural, social and economic aspects. The purpose of the assessment is to ensure that decision makers consider the ensuing environmental impacts to decide whether to proceed with the project. | An '''environmental impact assessment (EIA)''' is an assessment of the possible impact - positive or negative - that a proposed project may have on the environment, considering natural, social and economic aspects. The purpose of the assessment is to ensure that decision makers consider the ensuing environmental impacts to decide whether to proceed with the project. | ||
Line 6: | Line 6: | ||
<br/> | <br/> | ||
− | = | + | = Environmental Impacts of Small Hydro Power Projects<br/> = |
Small, run-of-the-river projects are free from many of the environmental problems associated with their large-scale relatives because they use the natural flow of the river, and thus produce relatively little change in the stream channel and flow. The dams built for some run-of-the-river projects are very small and impound little water - and many projects do not require a dam at all. Thus, effects such as oxygen depletion, increased temperature, decreased flow, and rejection of upstream migration aids like fish ladders are not problems for many run-of-the-river projects<ref>Small Hydropower Systems (Dept. of Energy USA, 2001): http://www.nrel.gov/docs/fy01osti/29065.pdf</ref>. | Small, run-of-the-river projects are free from many of the environmental problems associated with their large-scale relatives because they use the natural flow of the river, and thus produce relatively little change in the stream channel and flow. The dams built for some run-of-the-river projects are very small and impound little water - and many projects do not require a dam at all. Thus, effects such as oxygen depletion, increased temperature, decreased flow, and rejection of upstream migration aids like fish ladders are not problems for many run-of-the-river projects<ref>Small Hydropower Systems (Dept. of Energy USA, 2001): http://www.nrel.gov/docs/fy01osti/29065.pdf</ref>. | ||
− | [http://www.iitr.ac.in/departments/AH/uploads/File/International conference on SHP Kandy Srilanka All Details/Papers/Environmentsal Aspects-B/B22.pdf | + | |
+ | |||
+ | = Case Studies = | ||
+ | |||
+ | *[http://www.iitr.ac.in/departments/AH/uploads/File/International conference on SHP Kandy Srilanka All Details/Papers/Environmentsal Aspects-B/B22.pdf Environmental Impacts of Small Hydro Power Projects - India] | ||
<br/> | <br/> | ||
− | + | <br/> | |
+ | = Further Information<br/> = | ||
+ | |||
+ | *[[Portal:Hydro|Hydro Portal on energypedia]] | ||
*[http://en.wikipedia.org/wiki/Environmental_impact_assessment EIA in Wikipedia] | *[http://en.wikipedia.org/wiki/Environmental_impact_assessment EIA in Wikipedia] | ||
*[http://ec.europa.eu/environment/eia/home.htm EIA in the European Commission] | *[http://ec.europa.eu/environment/eia/home.htm EIA in the European Commission] | ||
Line 21: | Line 28: | ||
*[http://go.worldbank.org/OSARUT0MP0 Environmental Assessment by the World Bank] | *[http://go.worldbank.org/OSARUT0MP0 Environmental Assessment by the World Bank] | ||
*[http://www.adb.org/Documents/Guidelines/Environmental_Assessment/default.asp Environmental Assessment by the Asian Development Bank] | *[http://www.adb.org/Documents/Guidelines/Environmental_Assessment/default.asp Environmental Assessment by the Asian Development Bank] | ||
+ | *[http://www.nrel.gov/docs/fy01osti/29065.pdf Small Hydropower Systems (Dept. of Energy USA, 2001)] | ||
+ | |||
+ | <br/> | ||
− | + | = References = | |
<references /> | <references /> | ||
+ | [[Category:Impacts]] | ||
+ | [[Category:Impacts_Environmental]] | ||
[[Category:Hydro]] | [[Category:Hydro]] |
Revision as of 16:51, 22 September 2014
Introduction
An environmental impact assessment (EIA) is an assessment of the possible impact - positive or negative - that a proposed project may have on the environment, considering natural, social and economic aspects. The purpose of the assessment is to ensure that decision makers consider the ensuing environmental impacts to decide whether to proceed with the project.
Environmental Impacts of Small Hydro Power Projects
Small, run-of-the-river projects are free from many of the environmental problems associated with their large-scale relatives because they use the natural flow of the river, and thus produce relatively little change in the stream channel and flow. The dams built for some run-of-the-river projects are very small and impound little water - and many projects do not require a dam at all. Thus, effects such as oxygen depletion, increased temperature, decreased flow, and rejection of upstream migration aids like fish ladders are not problems for many run-of-the-river projects[1].
Case Studies
Further Information
- Hydro Portal on energypedia
- EIA in Wikipedia
- EIA in the European Commission
- EIA in a Transboundary Context - Espoo Convention
- Environmental Assessment by the World Bank
- Environmental Assessment by the Asian Development Bank
- Small Hydropower Systems (Dept. of Energy USA, 2001)