Difference between revisions of "Economic Analyses of Wind Energy Projects"
***** (***** | *****) |
***** (***** | *****) |
||
Line 103: | Line 103: | ||
With a specific HFO price of 11.88 USD/GJ and a net plant heat rate of 8,839 kJ/kWh, the specific fuel cost is 0.106 USD/kWh. | With a specific HFO price of 11.88 USD/GJ and a net plant heat rate of 8,839 kJ/kWh, the specific fuel cost is 0.106 USD/kWh. | ||
− | ==== Avoided non-Fuel Costs<br> ==== | + | ==== Avoided non-Fuel Costs<br> ==== |
Depending on the plant load factor, operating hours and fuel price, the fuel costs represents more than 80% of the total operation costs of a DPP. The remaining costs, the (non-) fuel O&M costs consist of fixed and variable costs. The fixed O&M costs include all those cost items which will be incurred irrespective of an operation of the plants operation status. | Depending on the plant load factor, operating hours and fuel price, the fuel costs represents more than 80% of the total operation costs of a DPP. The remaining costs, the (non-) fuel O&M costs consist of fixed and variable costs. The fixed O&M costs include all those cost items which will be incurred irrespective of an operation of the plants operation status. | ||
− | These fixed costs include costs for personnel, insurance, management and administration, as well as general maintenance costs. The general maintenance cost component includes costs of administration for services, consumables, materials, supplies procured, costs of postage, telephone, facsimile, reproductions and travel expenses.<br>The variable O&M costs include such cost components which are only incurred if the plant is operating. These costs comprise of lubrication oil and other consumables like chemicals, etc. Variable costs for the power plant also include the cost for overhauls including spare parts.<br>Each diesel engine has to undergo service and maintenance every 1500/3000/6000/12000/24000 and 36000/48000 operation hours. After 12000/24000 and 36000/48000 operation hours the diesel engines undergo major maintenance works, which are very cost intensive. This means that the below mentioned specific variable O&M costs (6 USD/MWh) for HFO operated DPP s of similar design and configuration is an average value calculated within one whole operation cycle until major overhaul at 36000/48000 operation hours.<br>EEPCos figures on variable and fixed O&M costs provided for the reference years 2004 to June 2006 are very low, even considering that the power plant has recently started commercial operation. Among other reasons, this is due to a low plant load factor. Since the annual fix non-fuel O&M costs provided by EEPCo could not be considered as representative for the whole period of analysis31, moderate international standard cost estimates settled at 100.000 USD for fix non-fuel O&M costs per year were applied in the economic analysis.<br>The estimation of avoided non-fuel variable O&M costs per year for the Diesel Power Plant has been considered according to the Consultant s experience from similar African Diesel Power Plants and according the following data:<br><br> | + | These fixed costs include costs for personnel, insurance, management and administration, as well as general maintenance costs. The general maintenance cost component includes costs of administration for services, consumables, materials, supplies procured, costs of postage, telephone, facsimile, reproductions and travel expenses.<br>The variable O&M costs include such cost components which are only incurred if the plant is operating. These costs comprise of lubrication oil and other consumables like chemicals, etc. Variable costs for the power plant also include the cost for overhauls including spare parts.<br>Each diesel engine has to undergo service and maintenance every 1500/3000/6000/12000/24000 and 36000/48000 operation hours. After 12000/24000 and 36000/48000 operation hours the diesel engines undergo major maintenance works, which are very cost intensive. This means that the below mentioned specific variable O&M costs (6 USD/MWh) for HFO operated DPP s of similar design and configuration is an average value calculated within one whole operation cycle until major overhaul at 36000/48000 operation hours.<br>EEPCos figures on variable and fixed O&M costs provided for the reference years 2004 to June 2006 are very low, even considering that the power plant has recently started commercial operation. Among other reasons, this is due to a low plant load factor. Since the annual fix non-fuel O&M costs provided by EEPCo could not be considered as representative for the whole period of analysis31, moderate international standard cost estimates settled at 100.000 USD for fix non-fuel O&M costs per year were applied in the economic analysis.<br>The estimation of avoided non-fuel variable O&M costs per year for the Diesel Power Plant has been considered according to the Consultant s experience from similar African Diesel Power Plants and according the following data:<br><br> |
{| cellspacing="1" cellpadding="1" border="1" align="center" width="600" | {| cellspacing="1" cellpadding="1" border="1" align="center" width="600" | ||
− | |+ '''Non-fuel variable O&M for a DPP''' | + | |+ '''Non-fuel variable O&M for a DPP''' |
|- | |- | ||
− | | Net plant capacity | + | | Net plant capacity |
| 38,000 kW | | 38,000 kW | ||
|- | |- | ||
− | | Assumed plant load factor, DPP as base load plant | + | | Assumed plant load factor, DPP as base load plant |
| 75 % | | 75 % | ||
|- | |- | ||
− | | Net plant energy production at HV side of step-up transformers | + | | Net plant energy production at HV side of step-up transformers |
| 249,660 MWh/year | | 249,660 MWh/year | ||
|- | |- | ||
− | | Specific variable O&M costs for HFO operated DPP s of similar<br>design and configuration all over the world (source Evaluation of<br>Institution of Diesel and Gas Turbine Engineers (IDGTE) Working<br>Cost and Operational Report 1997 | + | | Specific variable O&M costs for HFO operated DPP s of similar<br>design and configuration all over the world (source Evaluation of<br>Institution of Diesel and Gas Turbine Engineers (IDGTE) Working<br>Cost and Operational Report 1997 |
| 6 USD/MWh | | 6 USD/MWh | ||
|- | |- | ||
− | | Estimated annual expenditure for variable O&M costs | + | | Estimated annual expenditure for variable O&M costs |
| USD 1,497,960 | | USD 1,497,960 | ||
|} | |} | ||
− | < | + | ==== Avoided Emissions ==== |
+ | |||
+ | The avoided CO<sub>2</sub> emissions are calculated considering that a DPP with an efficiency of 43 % emits 670 gr. of CO<sub>2</sub> per kWh. The calculation follows the formula: | ||
+ | |||
+ | <math>670gCO_2/kWh \; at \; \nu=43\% \cdot Energy Output</math> | ||
+ | |||
+ | |||
+ | |||
+ | The results of applying the above formula to each Scenario are summarised in Table 12-6.<br>Table 12-6: Avoided emissions of the DPP<br><br>In the economic analysis the wind park is compared with a diesel power plant. Thus, the<br>avoided emissions refer to the DPP. The economic monetary quantification of the avoided<br>emissions has been based on the Mitigation Cost Approach. In the Mitigation Cost Approach,<br>the use of USD20/CO2 tonnes is considered as a reasonable estimate for the shadow price<br>of carbon emissions and it is consistent with the existing work by many experts:<br>Anderson et al. (1990, 1993) estimated a present-day USD25/CO2 tonnes shadow<br>price using a carbon accumulation-backstop technology model based on the Hotelling<br>rule;<br>Fankhauser (1995, 1996) estimates a global damage function for climate change, and<br>derives a range of USD6-45/CO2 tonnes shadow price, with a best estimate of<br>USD20/CO2 tonnes;<br>The Federation of American Scientists arrived at a shadow price of USD10-20/CO2<br>tonnes based on a Delphi-type assessment;<br>And simulations of the global carbon offset market performed by the Norwegian research<br>group, ECON, indicate a future market price for carbon of USD10-30/tC;<br>whereas in ADB's Economic Evaluation of Environmental Projects (March 1996), Appendix<br>H, Average Annual Global Climate Change Damages for Carbon Emissions<br>are estimated at USD7.85-USD17.66/CO2 tonnes for 1991 to 2000, increasing to 8.90<br>USD/CO2 tonnes - 20.03 USD/CO2 tonnes for 2011 to 2020, and decreasing thereafter.<br>The value has been also compared to the prices of CO2 emissions in the European Emissions<br>Trading System at the European Energy Exchange (EEX) based in Leipzig (Germany).<br>As showed in the figure below, prices have been over 20 / CO2 tonnes (24 USD/ CO2 tonnes)<br>almost all the time since October 200532, so that a price of 20 USD/ CO2 tonnes has<br>been applied in the economic analysis33.<br>32 VIK Mitgliedsrundschreiben 15/2006, March 3rd, 2006<br>33 In the financial analysis, current Certified Emission Reduction (CER) credit prices for Clean Development<br>Mechanism (CDM) activities have been considered at 6 USD/CER.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 197<br>final report mesobo-harena<br>CO2 certificate price development at the EEX<br>Figure 12-3: CO2 price development at EEX<br>12.2.6 Diesel Summary Assumptions<br>The basic parameters of the DPP used in the economic evaluation are summarised in the<br>following table.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 198<br>final report mesobo-harena<br>Table 12-7: Summary of basic assumptions of the reference DPP<br>Item Data Comment<br>Project Implementation Start Date 2006<br>Construction Period 18 months<br>Commercial Operation Date 2007<br>Tax and Duties Tax-free status<br>Exchange Rate ETB/USD 8.6199 : 1 Rate as per March 8th, 2006<br>Net Plant Capacity 38,000 kW<br>Plant Load Factor 75 %<br>Average Saleable Capacity 249,660 MWh/year This data has been adapted to<br>each windfarm s output<br>Capital Costs 817.61 USD/kW @site electrical net plant capacity<br>of 4 x 9,500 kW<br>Fixed non-fuel O&M Cost USD 100,000 p.a. As per EEPCo information<br>Variable non-fuel O&M Cost USD 1,497,960 p.a. = 6 USD/MWh<br>Heat rate 8,839 kJ/kWh @ LHV<br>Specific HFO180 Fuel Cost 0.10690<br>USD/kWhnet<br>share: 82 %<br>Specific LFO Fuel Cost 0.11589<br>USD/kWhnet<br>share: 18 %<br>The above mentioned assumptions have been applied in the Ashegoda Wind Park, whereas<br>in the Mesobo-Harena Wind Park lower capacities have been assumed.<br>Since the average saleable capacity of the reference DPP (249,660 MWh/year) is higher<br>than the estimated energy output of the Mesobo-Harena Wind Park, for comparison purposes<br>a lower net plant capacities for the reference DPP have been considered.<br>The size of the DPP that are estimated to produce the same output as the Mesobo-<br>Harena Wind Park and used in the calculation of the avoided capacity costs for each scenario<br>are specified in the table below:<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 199<br>final report mesobo-harena<br>Table 12-8: Required size of the DPP to produce the same output as the wind park<br>Finally, and for the small DPPs a higher fuel consumption of 210.0 g per generated kilo watt<br>hour at the alternator s terminals was considered, resulting in specific HFO fuel costs of<br>0.10845 USD/kWhnet and 0.11757 USD/kWhnet.<br>12.2.7 Indirect benefits<br>Main indirect benefits, that have not been quantified, but are to be considered are:<br>the fact that the injected wind energy reduces the absolute consumption of diesel<br>fuel, which is relatively expensive,<br>the generation of power will become more diversified,<br>the dependence on imported diesel fuel will decline,<br>the project confirms the energy-policy objectives of the Government of Ethiopia.<br>12.3 Economic Costs<br>In the economic analysis, the identified economic costs are (i) capital costs - investment<br>costs - of the wind park, (ii) operating costs of the wind power installation, and (iii) leakage<br>costs.<br>12.3.1 Investment Costs of the Wind Park<br>An itemised specification of investment costs (wind turbines, foundation, civil works, electrical<br>work, consulting services, physical and price contingencies, etc.) in actual prices broken<br>down in foreign and local cost components has been included in Section 9 Part I.<br>Internal prices in Ethiopia are considered to reflect an open market economy and do not<br>require further correction for distortions created by constraints of supply and demand in the<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 200<br>final report mesobo-harena<br>market. Based primarily on the conditions of foreign currency acquisition as well as to take<br>into account of the national allocation system of foreign currency, the Ministry of Economic<br>Development and Cooperation recommends that a shadow exchange rate factor of 1.11<br>would be applied. This leads to a standard conversion factor (SCF) of 0.9 is obtained for local<br>currency expenditure, effectively reducing local costs accordingly when expressed in foreign<br>currency units. Similar conversion factors were also applied in other recent studies carried<br>out for EEPCo34.<br>In the economic analysis the SCF of 0.9 has been applied to the expenditures in local currency,<br>resulting in total investment costs for the different wind park scenarios as detailed in<br>the following tables.<br>34 Feasibility Study of Weles, Zhemoga-Yeda and Halele-Werabesa Hydropower Project , Lahmeyer International<br>Gmh in association Mid-day Consulting Engineers and Tropic Consulting Engineers, June 2005.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 201<br>final report mesobo-harena<br>Table 12-9: Investment costs considering shadow prices<br>12.3.2 Economic O&M Costs of the Wind Park<br>The standard conversion factor (SCF) of 0.9 for local currency expenditure, effectively reducing<br>local costs accordingly when expressed in foreign currency units, has also been applied<br>to the O&M costs. To this end, O&M costs have been divided into foreign and local costs. For<br>maintenance and repair of the wind turbines it is assumed that after sufficient education of<br>the local operation team the work for these two activities can be executed to a significant<br>extend by the local personnel. For maintenance this portion is higher than for repairing since<br>for the repair procedures more specialized know-how is required and it has thus, to be carried<br>out by experienced wind energy foreign experts. (A further explanation is included in<br>Section 9.4). The following Tables include a detail of the annual O&M costs for the Mesobo -<br>Harena Wind Park considered in economic values.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 202<br>final report mesobo-harena<br>Table 12-10: Economic values of Enercon E48 annual O&M costs<br>Table 12-11: Economic values of Enercon E53 annual O&M costs<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 203<br>final report mesobo-harena<br>Table 12-12: Economic values of Vestas V52 annual O&M costs<br>Table 12-13: Economic values of Gamesa G58 annual O&M costs<br>Further, a major overhaul of all equipment has been assumed to take place between<br>the 10th and 11th years of operation in an amount of 5 % of total investment costs.<br>Also wind farm decommissioning costs in operational year 21 have been considered<br>with an amount of 1 % of total investment costs.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 204<br>final report mesobo-harena<br>12.3.3 Leakage Costs of the Wind Park<br>No leakage costs (or other external costs) could be identified for the wind park activity. Leakage<br>is defined by the United Nations Framework Convention on Climate Change (UNFCCC)<br>in its Guidelines for Completing CDM Project Design Documents, Version 02, as the net<br>change of antropogenic emissions by sources of GHG which occurs outside the project<br>boundary, and which is measurable and attributable to the project activity .<br>The project activity essentially involves the generation of electricity from wind, the employed<br>wind turbines can only convert wind energy into electrical energy and cannot use any other<br>input fuel for electricity generation. Thus, no fuel leakage cost occurs from the wind park project.<br>12.4 Results: Economic Analysis<br>The economic appraisal of the Mesobo-Hareba Wind Park has been carried out by comparing<br>the cash flow associated with construction and operation the wind power scheme with the<br>cash flow of construction and operation the equivalent least cost thermal alternative plant<br>(diesel power plant). In the appraisal, the avoided costs of thermal generation are regarded<br>as benefits attributable to the Wind Power Project. The difference between the costs of the<br>wind power project and the benefits of the avoided thermal power and energy has been determined<br>over a 20 year operational period. With regard to implementation of the wind power<br>plant, a fast-track schedule has been adopted. Only a fast-track schedule will come close<br>to meeting EEPCo s short and long-term strategic installed capacity target. Under the fasttrack<br>implementation schedule, construction probably will start at the end of 2006, with the<br>first energy feeding into the ICS in 2007. The results of the comparison of the proposed<br>Ashegoda Wind Power Project development with an equivalent DPP are shown in Table<br>12-14. Details of the cash flows of costs and benefits over the period are shown in Annex E.<br>Three main economic parameters have been used to evaluate the economic feasibility of the<br>wind park: the EIRR, the Benefit/Cost Ratio, and the ENPV calculated at a 10 % discount<br>rate.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 205<br>final report mesobo-harena<br>12.4.1 Economic Cash-flow Projections<br>Cash flow projections associated with construction and operation the wind parks have been<br>compared with the cash flow projections of construction and operation the equivalent least<br>cost thermal alternative plant, in this case, an emergency diesel power plant with nominal<br>capacities ranging from 14 MW to 16 MW depending on the estimated power output of the<br>wind park.<br>In the study, the avoided costs of thermal generation are regarded as benefits attributable to<br>the wind park project. The difference between the costs of the wind park project and the<br>benefits of the avoided thermal power and energy has been determined over a 20 year operational<br>period. Further the economic benefits of avoided emissions have been quantified.<br>12.4.2 EIRR and NPV<br>In this study, the EIRR is defined as the discount rate that causes the present value of the<br>project costs to be equal to the present value of the benefits. The EIRR indicates the actual<br>profit rate of the total investment outlay. The project is feasible if the EIRR is greater than the<br>agreed economic discount rate. It is given by the following equation:<br>i=1<br>n<br>net flow i<br>(1 + R )i-1<br>= 0<br>where n denotes calculation period (years) and R denotes discount rate.<br>As indicated in the assumptions, the discount rates for the basic scenarios are 10 %.<br>The ENPV of an investment is the present (discounted) value of future cash inflows<br>minus the present value of the investment and any associated future cash outflows.<br>The ENPV of the Ashegoda Wind Park has been calculated at different discount<br>rates (8 %, 10 % and 12 %). Results are indicated in the table below.<br>12.4.3 B/C Ratio<br>In the Benefit/Cost (B/C) Ratio, the total discounted benefits are divided by the total discounted<br>costs. Projects with a benefit-cost ratio greater than 1 have greater benefits than<br>costs as well as positive net benefits. The higher the ratio, the greater are the benefits relative<br>to the costs.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 206<br>final report mesobo-harena<br>Table 12-14: Results economic analysis Mesobo - Harena Wind Park<br>The results of the economic analysis are positive, showing that the wind park in all four Scenarios<br>and at a discount rate of 10 % is economically feasible. The highest results are produced<br>by the Scenario with the Gamesa G58 followed by the Scenario with Enercon E53<br>wind turbines, Scenario I with Enercon E48 and Scenario III with Vestas V52.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 207<br>final report mesobo-harena<br>12.5 Scenario Analysis<br>A scenario analysis has been carried out for the wind park scenario with the highest EIRR,<br>highest B/C Ratio and highest net benefits, i.e., the Scenario IV (57 Gamesa G58 turbines).<br>Changes in (i) avoided capacity costs, (ii) diesel fuel prices, (iii) CO2 penalties and (iv) electricity<br>generation and their impact on the EIRR have been evaluated.<br>Change in avoided Capacity Costs<br>As indicated previously, avoided capacity costs are calculated as the difference between<br>capacity costs of installing a DPP and the capacity costs of implementing a wind park. These<br>avoided capacity costs are negative since the investment costs of the wind park are higher<br>than the costs of the DPP.<br>The effect of increasing and reducing the wind park investment costs has been studied in two<br>cases:<br>Best Case: Investment costs 10 % lower than in the Base Case.<br>Worst Case: Investment costs 10 % higher than in the Base Case.<br>Change in Fuel Prices<br>Oil prices oscillate along the time. (Figure 12-4 for the development of the crude price in USD<br>per barrel (bbl) from April 2004 to March 200635).<br>35 Source: www.tecson.de<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 208<br>final report mesobo-harena<br>Figure 12-4: Crude price (USD/bbl) from April 2004 to March 2006<br>The impact of oil price variations (i.e., oscillations in the HFO crude oil price at DPP<br>516.45 USD/Mt and in the LFO oil price at DPP 559.87 USD/Mt-) , have been<br>analysed in the scenario analyses by modelling two cases:<br>Best Case: with an annual increase of 2 % on HFO & LFO prices at the DPP;<br>Worst Case: with an annual decrease of 2 % HFO & LFO prices at the DPP.<br>reflects the three scenarios used in the economic analysis, where in year 2028 HFO<br>prices are expected to increase until 798.42 USD/Mt and LFO until 865.55 USD/Mt<br>in the Best Case and to decrease until 331.13 USD/Mt for HFO and 358.97 USD/Mt<br>for LFO in the Worst Case.<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 209<br>final report mesobo-harena<br>Figure 12-5: Scenario analysis: HFO and LFO price development<br>Change in Emission (CO2) Penalties<br>Two cases have been tested in the scenario analysis in the costs of mitigating CO2 emissions<br>(penalties for emitting CO2), which were set at 20 USD/t in the base case:<br>Best Case: emissions penalty is set at 25 USD/t and<br>Worst Case: emissions penalty is set at 15 USD/t.<br>Change in Electricity Generation<br>The base case has been calculated assuming a Probability of Exceedance of 75 % (P75).<br>For the scenario analysis two further cases have been considered:<br>Best Case: Probability of Exceedance of 50 % (P50);<br>Worst Case: Probability of Exceedance of 90 % (P90).<br>A definition of the Probability of Exceedance can be found in Section 7 (Energy Production<br>Estimation).<br>12.5.1 Results: Economic Scenario Analysis<br>The scenario analysis shows that the variable with the highest impact on the EIRR is the<br>investment cost of the wind park followed by the electricity generation estimates. The best<br>results are obtained when decreasing investment costs by 10 %, whereas the impact on<br>20.00<br>120.00<br>320.00<br>420.00<br>520.00<br>620.00<br>720.00<br>820.00<br>920.00<br>2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028<br>Year<br>USD/Mt<br>Base Case (HFO) Best Case (HFO) Worst Case (HFO)<br>Base Case (LFO) Best Case (LFO) Worst Case (LFO)<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 210<br>final report mesobo-harena<br>EIRR of increasing emission penalties is from an economic point of view very low. The<br>following table summarises the results obtained in the sensitivity analysis.<br>Table 12-15: Summary Results of Scenario Analysis<br>12.6 Conclusions: Economic Analysis<br>The economic appraisal of the Mesobo - Harena Wind Park scheme has been carried out by<br>comparing the cash flow associated with construction and operation the wind park with the<br>cash flow of construction and operation the equivalent least cost thermal alternative plant36.<br>In the appraisal, the avoided costs of thermal generation are regarded as benefits attributable<br>to the Mesobo - Harena Wind Park Project. The difference between the costs of the<br>Mesobo - Harena project and the benefits of the avoided thermal power and energy has<br>been determined over a 20 year operational period37. With regard to implementation of the<br>wind park, a fast track schedule has been adopted. Only a fast track schedule will come<br>close to meet EEPCO s short and long-term strategic installed capacity target. Under the fast<br>track implementation, construction proper will start in 2007, with the first energy feeding into<br>the ICS in 2007.<br>The comparison of the proposed Wind Power Project with an equivalent thermal plant has<br>been made for 4 different Scenarios (Enercon E48, Enercon E53, Vestas V52 and Gamesa<br>36 The least costs thermal alternative plant has been defined by EEPCo as a Diesel Power Plant.<br>37 Cash-flows are presented for 20 year operational period plus decommissioning in year 21.<br>Scenario Analy-<br>Variable sis<br>Best Case Worst Case<br>Avoided capacity costs EIRRInv(-10%<br>)<br>= 19.36% EIRRInv(+10%<br>)<br>= 14.46%<br>Change in fuel prices EIRRFuel Price(+<br>2%)<br>.<br>. = 19.76% EIRRFuel<br>Price(<br>-2%<br>)<br>= 13.45%<br>Emission penalties EIRR<br>(25USD/t)<br>= 17.35% EIRR<br>(15USD/t)<br>= 15.93%<br>Electricity Generation (P) EIRR<br>(P50)<br>= 19.35% EIRR<br>(P90)<br>= 14.13%<br>Feasibility Study for Wind Park Development in Ethiopia and Capacity Building<br>Mesobo-Harena Wind Park Site<br>August 2006, Final Report - page 211<br>final report mesobo-harena<br>G58). The results (Table 12-14) show that all scenarios are economically feasible, being the<br>best Scenario the wind park with Gamesa G58 wind turbines followed by Enercon turbines<br>type E53 and E48. Since all the scenarios produce an EIRR higher than the discount rate of<br>10 % settled by the Ministry of Economic Development and Co-operation38 for Ethiopia, all<br>the scenarios can be considered as economically feasible.<br>For the Scenario with the highest produced results, (Scenario IV with Gamesa wind turbines)<br>a sensitivity analysis has been carried out. Four variables have been subject to the sensitivity<br>analysis: (i) changes in avoided capital costs through an increase /decrease on the investment<br>costs of the wind park in +10 %/-10 %; (ii) changes of fuel prices, i.e., an annual increase/<br>decrease on fuel prices of +2 %/-2 %; (iii) an increase/decrease of the emission penalties<br>from 20 USD/t considered in the base case scenario to 25 USD/t and 15 USD/t considered<br>in the best and worst cases, respectively; and finally, (iv) an increase/decrease in electricity<br>output.<br>The results of the economic sensitivity analysis have shown that changes on the investment<br>costs of the wind park have the major influence on the economic results. If the investment<br>costs could be negotiated and reduced by 10 %, the EIRR would increase from 16.64 % to<br>19.36 %. ==<br> | ||
<br> | <br> |
Revision as of 21:18, 20 July 2011
Methodology of a project analyses from a system perspective
Following the World Bank Handbook for Economic Analysis of Investment Operations[1], the main purpose of an economic analysis is to help to design and select projects that contribute to the welfare of a country. Whereas the financial analysis evaluates the project from the point of view of the operating company or Independent Power Producer (IPP), the economic
analysis evaluates the project from the point of view of the whole economy of the country.
The purpose of the investigation is to compare from a macroeconomic standpoint the benefits of the project with the costs it incurs, as is customary in any cost-benefit analysis. The standard of evaluation for costs and benefits is a monetary quantification. To the greatest possible extent, the project impacts are evaluated in terms of economic market prices. Shadow prices are employed, i.e., internal accounting prices that free the day-to-day (market) prices from multifarious biases. In other words, shadow prices represent an attempt to illuminate the actual costs of a product or service for the economy as a whole. In comparison with micro- and macro-economic prices, shadow prices are devoid of taxes and charges, duties and subsidies.
The economic analysis is conducted in the form of equalising the value of getting wind farms introduced to the power system to the induced savings in the power system in terms of avoided costs of thermal power generation. The incremental economic cost of the wind farm output is defined as the difference between the economic costs of the wind farm and the avoided economic cost (economic benefits) of a fossil power plant, which can be regarded as 'business as usual'-case for the country the analysis is applied for. As this article is based on a feasibility study for a wind park project in ethiopia[2], the power plant used for comparison is a diesel power plant.
The economic benefits or the costs of power generation with a (diesel) power plant comprise:
- capital costs of the plant;
- fuel costs;
- variable and fixed operating costs;
- external costs of (diesel) power generation.
These categories fit for most other types of fossil fuel driven plants. As diesel power plants are a very common type of generation unit in developing countries this example should be used in this article[3].
The economic costs for power generation with the wind energy project are accounted for:
- capital costs of the wind park,
- fixed operating costs of the wind power installation,
- external costs of wind power generation - leakage costs
From an economic point of view, the project is profitable, if during the period of time in question the cost of generating electricity with the wind park is lower than the cost of generating electricity with the diesel power plant. In other words: the costs incurred
for building and operating the discussed wind park must be lower than the utility value, or economic benefits, which it provides. The economic benefits are measured here in terms of avoided costs (savings). If the wind park is built, the operating costs, and the external costs, of diesel-based power generation will be avoided.
Pertinent to the cost categories for the diesel systems, differentiation can be made for the following economising effects:
- Capital effects: These account for savings on capital costs and fixed operating costs, because the result is, thanks to the wind power project, less money will have to be spent on new equipment and spare parts for the diesel power plants.
- Fuel and lubrication oil substitution. The wind turbines avoid fuel consumption of the diesel system. The difference between non-fuel operating costs of the diesel power plant and O&M costs of the wind park is also accounted for here.
- External effects. These stand for the reduced level of harmful emissions.
Since costs and benefits arise at different points in time, the time factor must be accounted for in the form of cash-flow discounting, hence bringing costs and benefits in line with a uniform initial date. A so-called standard discount rate (SDR) is used for discounting. The SDR is defined as the interest rate at which the company discounts a marginal future increase in consumption to its present value. This makes it possible to summarise and compare costs and benefits, each as a single factor.
The following profitability criteria can be used to quantify the outcome of the economic analysis:
- Benefits-cost ratio (B/C). The present values of the benefits are divided by the present values of the costs, and the project is profitable if the resultant benefits-cost ratio is greater than one.
- Economic Internal Rate of Return (EIRR). The internal interest is the social discount rate at which the present values of costs and benefits are equal.
- Economic Net Present Value (ENPV). Present value is the financial-mathematical expression used for the sum of the discounted values of a time series. The net present value is the difference between the present value of the benefits and the present value of the costs. The project is profitable, if the net present value is positive.
The discount rate (the opportunity cost of capital) applied in the calculation of the ENPV must be determined to calculate the economic benefits of a project. Its value depends on local market conditions, especially common interest rates and other financial parameters in the project country. In the feasibility study for Ethiopia the discount rate has been set at 10 %, in accordance with conversations held with the national electricity utility. Also, this rate was considered by the Ministry of Economic Development and Co-operation as appropriate for Ethiopia at the time of the study (2006). The indicated discount rate has also been applied in other recent feasibility studies carried out for Ethiopia
Economic Benefits
In the economic analysis the identified benefits are:
- (i) the avoided capital costs,
- (ii) the avoided fuel costs,
- (iii) avoided O&M costs and
- (iv) the avoided emissions.
Basic Diesel Power Plant Data
As already mentioned, the basic data for this study was based on one existing Diesel Power Plant located in the northern part of Ethiopia. This heavy fuel operated DPP commenced commercial operation in July 2004. The plant consists of four state-of-the-art 18 cylinder, V-type, 4-stroke, medium speed Wärtsilä diesel engines type 38 coupled to ABB alternators: each genset is rated at 9,991 kW (site capacity at alternator terminals). The net plant capacity exported to the grid at full load is 38 MW. The production and the sale of Wärtsilä type 38 diesel gensets was stopped by Wärtsilä within the course of strengthening Wärtsiläs engine and alternator portfolio. The type 38 was replaced by the type 46. The Wärtsilä 12V46 genset has a similar capacity as the 18V38
genset. The engine speed of the type 46 is 500 rpm.
Avoided Capital Costs
The economic feasibility is determined comparing a wind project with an equivalent diesel power plant alternative. The wind parks relative to the equivalent diesel based generation has been considered in terms of energy production. If the wind park would not be installed, additional energy would have to be provided by new diesel generators at higher costs.
The chosen DPP is especially suited for the analysis, since its annual generation is similar to the estimated energy production of the wind park. The capacities of the diesel units at this power plant have to be adapted to the prevailing site conditions. For comparison with the Ethipian wind project the DPP capacities are derated. Due to the importance of this fact, for the correct interpretation of the calculated capital costs and operation costs, the influence of the site conditions on the engines capacity have to be further analysed. If a wind energy project should be compared to another type of fossil fuel plants, information about the sensitivity of this plant (e.g. a gas-turbine) towards site conditions has to be gathered.
Diesel engines are internal combustion engines whose capacity is mainly influenced by the following site conditions:
- altitude of the site,
- combustion and
- cooling air temperature.
ISO 3046 Part 1 specifies the standard reference conditions, declarations of power, consumption and test methods for diesel engines. The ISO standard reference conditions are used as normative conditions for all diesel engines. The ISO conditions are as follows:
- Barometric pressure: 100 kPa (corresponds to 100 m altitude)
- Air temperature: 25°C
- Relative humidity: 30%
- Charge air coolant temperature: 25°C
Except for the humidity value, an increase of these values results in reduced capacity of the diesel engine. ISO 3046 Part 1 specifies also the algorithms for the derating calculations. The site reference conditions for the Ethiopian site for the regarded DPP are as follows:
- Site altitude: 1,200 m
- Air temperature: 30°C
- Relative humidity: 30% (estimated)
- Charge air coolant temperature: 40°C
The ISO capacity at alternator terminals of each Wärtsilä unit is 11,058 kW. The site capacity is 9,991 kW. This comparison shows, that each diesel genset is derated by 9.65% due to the site conditions, mainly due to the site altitude. This diesel power plant would deliver approximately 9.65% more capacity, if it was installed between 0 and 300 meters above sea level. This comparison is important for the interpretation of the result of the economic analysis, since the derated capacity of the plant increases the specific costs of the plant compared to a non-derated plant by approximately 9-10%.
- The gross plant capacity (= at alternator terminals) is 4 x 9,991 kW = 39,964 kW.
- The net plant capacity (= capacity exported to the grid) is 4 x 9,500 kW = 38,000 kW.
- The difference between both values (= 1,964 kW = 4.9%) is the auxiliary power consumption of
the plant.
The avoided capacity costs refer to the investment costs that would occur when installing a DPP like the investigated 40 MW plant. The avoided capacity costs were calculated at USD 817.61/kW. Due to strong continued demand for diesel power plants over the last few years, and limited production capacity of the diesel engine & genset manufacturers, the specific costs of diesel power plants (EPC contracts) are slightly, though continuously increasing.
Avoided Fuel Costs
A possibility to determine fuel costs is calculation by fuel prices and the fuel consumption of the diesel gensets[4]. The fuel prices have to be calculated as delivered to the site. The considered DPP in the Ethiopian feasibility study is laid out for continuous operation on cheap heavy fuel oil (HFO). Expensive light fuel oil (LFO) is only needed as back-up fuel: used during start-up and shut
down of the diesel engines, and when HFO is not available due to technical problems of the transfer and/or fuel treatment systems.
For the case of the Ethipian site HFO is a residual oil produced during the refinery process of crude oil. It has a lower quality and higher viscosity than LFO and consequently a lower price than LFO.
Depending on its viscosity, HFO must be kept heated during transport in order to avoid problems during loading and unloading due to high viscosity.
The light fuel (LFO) used at the considered DPP varies between 45 and 80 centi Stokes (cSt) at 50°C, and the HFO used, has a maximum viscosity of 180 cSt at 50°C. The annual fuel consumption recorded in the operation log books of the regarded DPP can
be divided as follows:
- HFO consumption: 82%
- LFO consumption: 18%
Considering the same lower heating value (LHV) for HFO and LFO, the above mentioned percentages do not need to be corrected and can be directly used for the fuel consumption cost calculations. The fuel consumption of diesel units of a state-of-the-art DPP is measured by means of volumetric fuel flow meters with thermal correction and automatic data transfer to the control system of the plant (history/data record). Together with the produced energy (kWh; GWh) a specific fuel consumption can be calculated, which is normally given in g/kWh, referred to the alternator s terminal.
Fuel losses occurring during the fuel treatment (water & sediment drainage, separation and filtering of fuel) should be added to the above mentioned specific consumption, since the lost fuel/water/sediment volume was also purchased by the Owner. These losses were estimated in this case to 3% of the specific consumption.
The fuel consumption is normally based on a LHV of fuel of 42.7 MJ/kg. Other LHV values can be also applied by calculating the specific consumption by means of a linear relation between the two LHVs.
The fuel consumption of a diesel genset is also subject to derating based on the prevailing site conditions like the gensets capacity. The gensets consumption is normally given as ISO based value and as site based value. In case of the Wärtsilä 18V38 genset, the ISO fuel consumption is 182.1 g/kWh (@ LHV 42.7 MJ) at the alternators terminals, ±5% tolerance.
This represents an electrical efficiency of the gensets of 46.3% at ISO conditions. Considering the site conditions, the site fuel consumption of each unit is 200.3 g/kWh (@LHV 42.7 MJ) at the alternator s terminals, ±5% tolerance. This represents an electrical efficiency at site of the genset of 42.1 %.
Including 3% losses inside the plant, the net plant fuel consumption of each genset is 206.3g/kWh (@ LHV 42.7 MJ). Including 5% tolerance the value is 216.6 g/kWh.
For the economic analysis a fuel consumption of 207.0 g per generated kilo watt hour at the alternator s terminals was considered. This corresponds to a net plant heat rate of 8,839 kJ/kWh. Fuel prices vary strongly, proportional to the volatile price development of crude oil prices. The fuel oil prices consists normally of the following components:
- Fuel price at port of loading
- Cost of sea transport and insurance
- Cost at port of unloading: pumping, taxes, transport to fuel depot
- Cost of land transport (tank truck) and insurance
According to the national electricity utility (EEPCO), the HFO 180 price at Djibouti harbour (Ethiopia) amounted to 3.6949 ETB per litre as per May 2006. Considering the above mentioned density and an exchange rate of 1 USD = 8.61 ETB, the price of HFO 180 is 446.51 USD/Mt. The price for LFO at Djibouti port is 3.7754 ETB per litre corresponding to USD 0.4379. With a maximum density of 0.90, the metric ton is equivalent to 1,111.1litres. Consequently, the LFO price is 486.65 USD/Mt.
The fuel finally delivered by dealers from the depot to the considered DPP has the following price increment covering the transport, service charges and profit of the dealers:
- HFO: 0.4151 ETB/liter = USD 50.16/Mt[5]
- LFO: 0.4146 ETB/liter = USD 53.44/Mt
The final fuel prices at the regarded DPP are as follows:
- HFO: USD 516.45 /Mt = USD 0.4958/litre = 4.2737 ETB/liter
- LFO: USD 559.87 /Mt = USD 0.5039/litre = 4.3435 ETB/liter
With a specific HFO price of 11.88 USD/GJ and a net plant heat rate of 8,839 kJ/kWh, the specific fuel cost is 0.106 USD/kWh.
Avoided non-Fuel Costs
Depending on the plant load factor, operating hours and fuel price, the fuel costs represents more than 80% of the total operation costs of a DPP. The remaining costs, the (non-) fuel O&M costs consist of fixed and variable costs. The fixed O&M costs include all those cost items which will be incurred irrespective of an operation of the plants operation status.
These fixed costs include costs for personnel, insurance, management and administration, as well as general maintenance costs. The general maintenance cost component includes costs of administration for services, consumables, materials, supplies procured, costs of postage, telephone, facsimile, reproductions and travel expenses.
The variable O&M costs include such cost components which are only incurred if the plant is operating. These costs comprise of lubrication oil and other consumables like chemicals, etc. Variable costs for the power plant also include the cost for overhauls including spare parts.
Each diesel engine has to undergo service and maintenance every 1500/3000/6000/12000/24000 and 36000/48000 operation hours. After 12000/24000 and 36000/48000 operation hours the diesel engines undergo major maintenance works, which are very cost intensive. This means that the below mentioned specific variable O&M costs (6 USD/MWh) for HFO operated DPP s of similar design and configuration is an average value calculated within one whole operation cycle until major overhaul at 36000/48000 operation hours.
EEPCos figures on variable and fixed O&M costs provided for the reference years 2004 to June 2006 are very low, even considering that the power plant has recently started commercial operation. Among other reasons, this is due to a low plant load factor. Since the annual fix non-fuel O&M costs provided by EEPCo could not be considered as representative for the whole period of analysis31, moderate international standard cost estimates settled at 100.000 USD for fix non-fuel O&M costs per year were applied in the economic analysis.
The estimation of avoided non-fuel variable O&M costs per year for the Diesel Power Plant has been considered according to the Consultant s experience from similar African Diesel Power Plants and according the following data:
Net plant capacity | 38,000 kW |
Assumed plant load factor, DPP as base load plant | 75 % |
Net plant energy production at HV side of step-up transformers | 249,660 MWh/year |
Specific variable O&M costs for HFO operated DPP s of similar design and configuration all over the world (source Evaluation of Institution of Diesel and Gas Turbine Engineers (IDGTE) Working Cost and Operational Report 1997 |
6 USD/MWh |
Estimated annual expenditure for variable O&M costs | USD 1,497,960 |
Avoided Emissions
The avoided CO2 emissions are calculated considering that a DPP with an efficiency of 43 % emits 670 gr. of CO2 per kWh. The calculation follows the formula:
The results of applying the above formula to each Scenario are summarised in Table 12-6.
Table 12-6: Avoided emissions of the DPP
In the economic analysis the wind park is compared with a diesel power plant. Thus, the
avoided emissions refer to the DPP. The economic monetary quantification of the avoided
emissions has been based on the Mitigation Cost Approach. In the Mitigation Cost Approach,
the use of USD20/CO2 tonnes is considered as a reasonable estimate for the shadow price
of carbon emissions and it is consistent with the existing work by many experts:
Anderson et al. (1990, 1993) estimated a present-day USD25/CO2 tonnes shadow
price using a carbon accumulation-backstop technology model based on the Hotelling
rule;
Fankhauser (1995, 1996) estimates a global damage function for climate change, and
derives a range of USD6-45/CO2 tonnes shadow price, with a best estimate of
USD20/CO2 tonnes;
The Federation of American Scientists arrived at a shadow price of USD10-20/CO2
tonnes based on a Delphi-type assessment;
And simulations of the global carbon offset market performed by the Norwegian research
group, ECON, indicate a future market price for carbon of USD10-30/tC;
whereas in ADB's Economic Evaluation of Environmental Projects (March 1996), Appendix
H, Average Annual Global Climate Change Damages for Carbon Emissions
are estimated at USD7.85-USD17.66/CO2 tonnes for 1991 to 2000, increasing to 8.90
USD/CO2 tonnes - 20.03 USD/CO2 tonnes for 2011 to 2020, and decreasing thereafter.
The value has been also compared to the prices of CO2 emissions in the European Emissions
Trading System at the European Energy Exchange (EEX) based in Leipzig (Germany).
As showed in the figure below, prices have been over 20 / CO2 tonnes (24 USD/ CO2 tonnes)
almost all the time since October 200532, so that a price of 20 USD/ CO2 tonnes has
been applied in the economic analysis33.
32 VIK Mitgliedsrundschreiben 15/2006, March 3rd, 2006
33 In the financial analysis, current Certified Emission Reduction (CER) credit prices for Clean Development
Mechanism (CDM) activities have been considered at 6 USD/CER.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 197
final report mesobo-harena
CO2 certificate price development at the EEX
Figure 12-3: CO2 price development at EEX
12.2.6 Diesel Summary Assumptions
The basic parameters of the DPP used in the economic evaluation are summarised in the
following table.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 198
final report mesobo-harena
Table 12-7: Summary of basic assumptions of the reference DPP
Item Data Comment
Project Implementation Start Date 2006
Construction Period 18 months
Commercial Operation Date 2007
Tax and Duties Tax-free status
Exchange Rate ETB/USD 8.6199 : 1 Rate as per March 8th, 2006
Net Plant Capacity 38,000 kW
Plant Load Factor 75 %
Average Saleable Capacity 249,660 MWh/year This data has been adapted to
each windfarm s output
Capital Costs 817.61 USD/kW @site electrical net plant capacity
of 4 x 9,500 kW
Fixed non-fuel O&M Cost USD 100,000 p.a. As per EEPCo information
Variable non-fuel O&M Cost USD 1,497,960 p.a. = 6 USD/MWh
Heat rate 8,839 kJ/kWh @ LHV
Specific HFO180 Fuel Cost 0.10690
USD/kWhnet
share: 82 %
Specific LFO Fuel Cost 0.11589
USD/kWhnet
share: 18 %
The above mentioned assumptions have been applied in the Ashegoda Wind Park, whereas
in the Mesobo-Harena Wind Park lower capacities have been assumed.
Since the average saleable capacity of the reference DPP (249,660 MWh/year) is higher
than the estimated energy output of the Mesobo-Harena Wind Park, for comparison purposes
a lower net plant capacities for the reference DPP have been considered.
The size of the DPP that are estimated to produce the same output as the Mesobo-
Harena Wind Park and used in the calculation of the avoided capacity costs for each scenario
are specified in the table below:
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 199
final report mesobo-harena
Table 12-8: Required size of the DPP to produce the same output as the wind park
Finally, and for the small DPPs a higher fuel consumption of 210.0 g per generated kilo watt
hour at the alternator s terminals was considered, resulting in specific HFO fuel costs of
0.10845 USD/kWhnet and 0.11757 USD/kWhnet.
12.2.7 Indirect benefits
Main indirect benefits, that have not been quantified, but are to be considered are:
the fact that the injected wind energy reduces the absolute consumption of diesel
fuel, which is relatively expensive,
the generation of power will become more diversified,
the dependence on imported diesel fuel will decline,
the project confirms the energy-policy objectives of the Government of Ethiopia.
12.3 Economic Costs
In the economic analysis, the identified economic costs are (i) capital costs - investment
costs - of the wind park, (ii) operating costs of the wind power installation, and (iii) leakage
costs.
12.3.1 Investment Costs of the Wind Park
An itemised specification of investment costs (wind turbines, foundation, civil works, electrical
work, consulting services, physical and price contingencies, etc.) in actual prices broken
down in foreign and local cost components has been included in Section 9 Part I.
Internal prices in Ethiopia are considered to reflect an open market economy and do not
require further correction for distortions created by constraints of supply and demand in the
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 200
final report mesobo-harena
market. Based primarily on the conditions of foreign currency acquisition as well as to take
into account of the national allocation system of foreign currency, the Ministry of Economic
Development and Cooperation recommends that a shadow exchange rate factor of 1.11
would be applied. This leads to a standard conversion factor (SCF) of 0.9 is obtained for local
currency expenditure, effectively reducing local costs accordingly when expressed in foreign
currency units. Similar conversion factors were also applied in other recent studies carried
out for EEPCo34.
In the economic analysis the SCF of 0.9 has been applied to the expenditures in local currency,
resulting in total investment costs for the different wind park scenarios as detailed in
the following tables.
34 Feasibility Study of Weles, Zhemoga-Yeda and Halele-Werabesa Hydropower Project , Lahmeyer International
Gmh in association Mid-day Consulting Engineers and Tropic Consulting Engineers, June 2005.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 201
final report mesobo-harena
Table 12-9: Investment costs considering shadow prices
12.3.2 Economic O&M Costs of the Wind Park
The standard conversion factor (SCF) of 0.9 for local currency expenditure, effectively reducing
local costs accordingly when expressed in foreign currency units, has also been applied
to the O&M costs. To this end, O&M costs have been divided into foreign and local costs. For
maintenance and repair of the wind turbines it is assumed that after sufficient education of
the local operation team the work for these two activities can be executed to a significant
extend by the local personnel. For maintenance this portion is higher than for repairing since
for the repair procedures more specialized know-how is required and it has thus, to be carried
out by experienced wind energy foreign experts. (A further explanation is included in
Section 9.4). The following Tables include a detail of the annual O&M costs for the Mesobo -
Harena Wind Park considered in economic values.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 202
final report mesobo-harena
Table 12-10: Economic values of Enercon E48 annual O&M costs
Table 12-11: Economic values of Enercon E53 annual O&M costs
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 203
final report mesobo-harena
Table 12-12: Economic values of Vestas V52 annual O&M costs
Table 12-13: Economic values of Gamesa G58 annual O&M costs
Further, a major overhaul of all equipment has been assumed to take place between
the 10th and 11th years of operation in an amount of 5 % of total investment costs.
Also wind farm decommissioning costs in operational year 21 have been considered
with an amount of 1 % of total investment costs.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 204
final report mesobo-harena
12.3.3 Leakage Costs of the Wind Park
No leakage costs (or other external costs) could be identified for the wind park activity. Leakage
is defined by the United Nations Framework Convention on Climate Change (UNFCCC)
in its Guidelines for Completing CDM Project Design Documents, Version 02, as the net
change of antropogenic emissions by sources of GHG which occurs outside the project
boundary, and which is measurable and attributable to the project activity .
The project activity essentially involves the generation of electricity from wind, the employed
wind turbines can only convert wind energy into electrical energy and cannot use any other
input fuel for electricity generation. Thus, no fuel leakage cost occurs from the wind park project.
12.4 Results: Economic Analysis
The economic appraisal of the Mesobo-Hareba Wind Park has been carried out by comparing
the cash flow associated with construction and operation the wind power scheme with the
cash flow of construction and operation the equivalent least cost thermal alternative plant
(diesel power plant). In the appraisal, the avoided costs of thermal generation are regarded
as benefits attributable to the Wind Power Project. The difference between the costs of the
wind power project and the benefits of the avoided thermal power and energy has been determined
over a 20 year operational period. With regard to implementation of the wind power
plant, a fast-track schedule has been adopted. Only a fast-track schedule will come close
to meeting EEPCo s short and long-term strategic installed capacity target. Under the fasttrack
implementation schedule, construction probably will start at the end of 2006, with the
first energy feeding into the ICS in 2007. The results of the comparison of the proposed
Ashegoda Wind Power Project development with an equivalent DPP are shown in Table
12-14. Details of the cash flows of costs and benefits over the period are shown in Annex E.
Three main economic parameters have been used to evaluate the economic feasibility of the
wind park: the EIRR, the Benefit/Cost Ratio, and the ENPV calculated at a 10 % discount
rate.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 205
final report mesobo-harena
12.4.1 Economic Cash-flow Projections
Cash flow projections associated with construction and operation the wind parks have been
compared with the cash flow projections of construction and operation the equivalent least
cost thermal alternative plant, in this case, an emergency diesel power plant with nominal
capacities ranging from 14 MW to 16 MW depending on the estimated power output of the
wind park.
In the study, the avoided costs of thermal generation are regarded as benefits attributable to
the wind park project. The difference between the costs of the wind park project and the
benefits of the avoided thermal power and energy has been determined over a 20 year operational
period. Further the economic benefits of avoided emissions have been quantified.
12.4.2 EIRR and NPV
In this study, the EIRR is defined as the discount rate that causes the present value of the
project costs to be equal to the present value of the benefits. The EIRR indicates the actual
profit rate of the total investment outlay. The project is feasible if the EIRR is greater than the
agreed economic discount rate. It is given by the following equation:
i=1
n
net flow i
(1 + R )i-1
= 0
where n denotes calculation period (years) and R denotes discount rate.
As indicated in the assumptions, the discount rates for the basic scenarios are 10 %.
The ENPV of an investment is the present (discounted) value of future cash inflows
minus the present value of the investment and any associated future cash outflows.
The ENPV of the Ashegoda Wind Park has been calculated at different discount
rates (8 %, 10 % and 12 %). Results are indicated in the table below.
12.4.3 B/C Ratio
In the Benefit/Cost (B/C) Ratio, the total discounted benefits are divided by the total discounted
costs. Projects with a benefit-cost ratio greater than 1 have greater benefits than
costs as well as positive net benefits. The higher the ratio, the greater are the benefits relative
to the costs.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 206
final report mesobo-harena
Table 12-14: Results economic analysis Mesobo - Harena Wind Park
The results of the economic analysis are positive, showing that the wind park in all four Scenarios
and at a discount rate of 10 % is economically feasible. The highest results are produced
by the Scenario with the Gamesa G58 followed by the Scenario with Enercon E53
wind turbines, Scenario I with Enercon E48 and Scenario III with Vestas V52.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 207
final report mesobo-harena
12.5 Scenario Analysis
A scenario analysis has been carried out for the wind park scenario with the highest EIRR,
highest B/C Ratio and highest net benefits, i.e., the Scenario IV (57 Gamesa G58 turbines).
Changes in (i) avoided capacity costs, (ii) diesel fuel prices, (iii) CO2 penalties and (iv) electricity
generation and their impact on the EIRR have been evaluated.
Change in avoided Capacity Costs
As indicated previously, avoided capacity costs are calculated as the difference between
capacity costs of installing a DPP and the capacity costs of implementing a wind park. These
avoided capacity costs are negative since the investment costs of the wind park are higher
than the costs of the DPP.
The effect of increasing and reducing the wind park investment costs has been studied in two
cases:
Best Case: Investment costs 10 % lower than in the Base Case.
Worst Case: Investment costs 10 % higher than in the Base Case.
Change in Fuel Prices
Oil prices oscillate along the time. (Figure 12-4 for the development of the crude price in USD
per barrel (bbl) from April 2004 to March 200635).
35 Source: www.tecson.de
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 208
final report mesobo-harena
Figure 12-4: Crude price (USD/bbl) from April 2004 to March 2006
The impact of oil price variations (i.e., oscillations in the HFO crude oil price at DPP
516.45 USD/Mt and in the LFO oil price at DPP 559.87 USD/Mt-) , have been
analysed in the scenario analyses by modelling two cases:
Best Case: with an annual increase of 2 % on HFO & LFO prices at the DPP;
Worst Case: with an annual decrease of 2 % HFO & LFO prices at the DPP.
reflects the three scenarios used in the economic analysis, where in year 2028 HFO
prices are expected to increase until 798.42 USD/Mt and LFO until 865.55 USD/Mt
in the Best Case and to decrease until 331.13 USD/Mt for HFO and 358.97 USD/Mt
for LFO in the Worst Case.
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 209
final report mesobo-harena
Figure 12-5: Scenario analysis: HFO and LFO price development
Change in Emission (CO2) Penalties
Two cases have been tested in the scenario analysis in the costs of mitigating CO2 emissions
(penalties for emitting CO2), which were set at 20 USD/t in the base case:
Best Case: emissions penalty is set at 25 USD/t and
Worst Case: emissions penalty is set at 15 USD/t.
Change in Electricity Generation
The base case has been calculated assuming a Probability of Exceedance of 75 % (P75).
For the scenario analysis two further cases have been considered:
Best Case: Probability of Exceedance of 50 % (P50);
Worst Case: Probability of Exceedance of 90 % (P90).
A definition of the Probability of Exceedance can be found in Section 7 (Energy Production
Estimation).
12.5.1 Results: Economic Scenario Analysis
The scenario analysis shows that the variable with the highest impact on the EIRR is the
investment cost of the wind park followed by the electricity generation estimates. The best
results are obtained when decreasing investment costs by 10 %, whereas the impact on
20.00
120.00
320.00
420.00
520.00
620.00
720.00
820.00
920.00
2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Year
USD/Mt
Base Case (HFO) Best Case (HFO) Worst Case (HFO)
Base Case (LFO) Best Case (LFO) Worst Case (LFO)
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 210
final report mesobo-harena
EIRR of increasing emission penalties is from an economic point of view very low. The
following table summarises the results obtained in the sensitivity analysis.
Table 12-15: Summary Results of Scenario Analysis
12.6 Conclusions: Economic Analysis
The economic appraisal of the Mesobo - Harena Wind Park scheme has been carried out by
comparing the cash flow associated with construction and operation the wind park with the
cash flow of construction and operation the equivalent least cost thermal alternative plant36.
In the appraisal, the avoided costs of thermal generation are regarded as benefits attributable
to the Mesobo - Harena Wind Park Project. The difference between the costs of the
Mesobo - Harena project and the benefits of the avoided thermal power and energy has
been determined over a 20 year operational period37. With regard to implementation of the
wind park, a fast track schedule has been adopted. Only a fast track schedule will come
close to meet EEPCO s short and long-term strategic installed capacity target. Under the fast
track implementation, construction proper will start in 2007, with the first energy feeding into
the ICS in 2007.
The comparison of the proposed Wind Power Project with an equivalent thermal plant has
been made for 4 different Scenarios (Enercon E48, Enercon E53, Vestas V52 and Gamesa
36 The least costs thermal alternative plant has been defined by EEPCo as a Diesel Power Plant.
37 Cash-flows are presented for 20 year operational period plus decommissioning in year 21.
Scenario Analy-
Variable sis
Best Case Worst Case
Avoided capacity costs EIRRInv(-10%
)
= 19.36% EIRRInv(+10%
)
= 14.46%
Change in fuel prices EIRRFuel Price(+
2%)
.
. = 19.76% EIRRFuel
Price(
-2%
)
= 13.45%
Emission penalties EIRR
(25USD/t)
= 17.35% EIRR
(15USD/t)
= 15.93%
Electricity Generation (P) EIRR
(P50)
= 19.35% EIRR
(P90)
= 14.13%
Feasibility Study for Wind Park Development in Ethiopia and Capacity Building
Mesobo-Harena Wind Park Site
August 2006, Final Report - page 211
final report mesobo-harena
G58). The results (Table 12-14) show that all scenarios are economically feasible, being the
best Scenario the wind park with Gamesa G58 wind turbines followed by Enercon turbines
type E53 and E48. Since all the scenarios produce an EIRR higher than the discount rate of
10 % settled by the Ministry of Economic Development and Co-operation38 for Ethiopia, all
the scenarios can be considered as economically feasible.
For the Scenario with the highest produced results, (Scenario IV with Gamesa wind turbines)
a sensitivity analysis has been carried out. Four variables have been subject to the sensitivity
analysis: (i) changes in avoided capital costs through an increase /decrease on the investment
costs of the wind park in +10 %/-10 %; (ii) changes of fuel prices, i.e., an annual increase/
decrease on fuel prices of +2 %/-2 %; (iii) an increase/decrease of the emission penalties
from 20 USD/t considered in the base case scenario to 25 USD/t and 15 USD/t considered
in the best and worst cases, respectively; and finally, (iv) an increase/decrease in electricity
output.
The results of the economic sensitivity analysis have shown that changes on the investment
costs of the wind park have the major influence on the economic results. If the investment
costs could be negotiated and reduced by 10 %, the EIRR would increase from 16.64 % to
19.36 %. ==
- ↑ World Bank (1996) Handbook on Economic AnalysisfckLRof Investment Operations, retrieved 19.7.2011 [[1]]
- ↑ The contents of this article have been prepared by the project team of the feasibility study of the Ethiopian wind park Mesobo-harena, conducted by the Deutsche Gesellschaft für internationale Zusammenarbeit (GIZ) in cooperation with the Austrian development agency and Lahmeyer international. Originally the contents have been published as: GTZ (2006) Feasibility Study for Wind Park Development in Ethiopia and Capacity Building - Mesobo-harena Wind Park Site), retrieved 11.7.2011
- ↑ The feasibility studyfckLRthe Consultant based the technical data and derived calculations for the capital costs of In the feasibility study for the Mesobo-Harena wind park in Ethiopia conducted by the Deutsche Gesellschaft für internationale Zusammenarbeit (GIZ) the diesel power plant, which is used as an example for the economic comparison with the wind park project, was based on one existing 40 MW diesel power plant (DPP) located in the northern part of Ethiopia. The financial data was adjusted where ever applicable to arrive at the estimated current market value of the existing plant.
- ↑ Distributed generator systems (gensets) are electric generating facilities that are sited at or near the electric user’s home or business. They may be integrated into the electric utility grid system so that the utility may be relied on for back-up power. In other cases, a genset may provide, at times, more power than is required by the host user and may deliver this power to the utility (often called “reverse metering”). Gensets may also provide emergency power for the host when there is a power outage on the grid. In other applications, gensets are placed off-grid – in rural farms or villages in undeveloped countries, for example.
- ↑ OECD (2006)