Knowledge fuels change - Support energypedia!
For over 10 years, energypedia has been connecting energy experts around the world — helping them share knowledge, learn from each other, and accelerate the global energy transition.
Today, we ask for your support to keep this platform free and accessible to all.
Even a small contribution makes a big difference! If just 10–20% of our 60,000+ monthly visitors donated the equivalent of a cup of coffee — €5 — Energypedia would be fully funded for a whole year.
Is the knowledge you’ve gained through Energypedia this year worth €5 or more?
Your donation keeps the platform running, helps us create new knowledge products, and contributes directly to achieving SDG 7.
Thank you for your support, your donation, big or small, truly matters!
Difference between revisions of "Costs of Micro-Hydro Power Sites"
***** (***** | *****) m (Fungai Cecilia Sandamu moved page Costs of MHP sites to Costs of Micro-Hydro Power Sites without leaving a redirect) |
***** (***** | *****) m (Reverted edits by Michel andre (*****) to last revision by *****) |
||
| (9 intermediate revisions by 4 users not shown) | |||
| Line 1: | Line 1: | ||
| − | MHP projects come along with a big variety of costs. Planning and developing a site brings a number of country, | + | = Overview<br/> = |
| + | |||
| + | '''Micro-Hydro Power (MHP)''' projects come along with a big variety of costs. Planning and developing a site brings a number of country, probably regional specific costs. Similar to that are costs for operation and maintenance. All different cost categories play a role for individual projects, while big difference between countries due to different framework condition might occur. A clear cost analysis upfront is highly recommended.<br/> | ||
| + | |||
| + | <br/> | ||
| + | |||
| + | = Costs = | ||
| + | |||
| + | <u>Cost Factors are Eventually:</u> | ||
| + | *<span lang="EN-US">a locations feasibility check by respective personal</span> | ||
| + | *<span lang="EN-US">land/water ownership/usage</span> | ||
| + | *<span lang="EN-US">civil construction (canal, wear, intake, pipes, powerhouse)</span> | ||
| + | *<span lang="EN-US">electro-mechanical equipment (turbine, generator, load controller)</span> | ||
| + | *power grid (evtl. transformers, powerlines, house-cabeling, load limiters, meter installation, ...) | ||
| + | *operation & maintenance (collecting tariffs, running and maintaining the assets) | ||
| + | |||
| + | <br/> | ||
| + | |||
| + | <u>Some remarks regarding costs:</u> | ||
| + | *<span lang="EN-US">Land & water requirements are mostly small. But there may be interference with existing schemes (irrigation) or legal issues to be considered.</span> | ||
| + | *Order to delivery of <span lang="EN-US"><u>electro-mechanical equipment</u> may</span> take half a year. Ensure to order in time. | ||
| + | *<span lang="EN-US">Costs for power lines and household connections often require a substantial amount from the overall budged.</span> | ||
| + | *<span lang="EN-US">Any mhp scheme supplying a group of households has to install fixed procedures to cover operation & maintenance.</span><br/> | ||
| + | *<span lang="EN-US">This includes the collection of tariffs from each user.</span> | ||
| + | |||
| + | <br/> | ||
| + | |||
| + | <br/> | ||
| + | |||
| + | == Example: Micro-Hydro Power (MHP) Costs in Rwanda<br/> == | ||
| + | *A special chapter about the [[Micro-Hydropower Plants - Estimation of Management Costs|management costs]] was developed, too. | ||
| + | |||
| + | |||
| + | |||
| + | -> [[Rwanda_Energy_Situation|Rwanda Energy Situation]] | ||
<br/> | <br/> | ||
| − | |||
| − | * | + | = Further Information = |
| − | * | + | |
| + | *[[Portal:Hydro|Hydro Portal on energypedia]]<br/> | ||
| + | *[[Micro-Hydro Power - Analysis of Costs|Micro-Hydro Power - Analysis of Costs]]<br/> | ||
| + | *[[Micro-Hydropower Plants - Estimation of Management Costs|Micro-Hydropower Plants - Estimation of Management Costs]] | ||
| + | |||
| + | |||
| + | |||
| + | = References<br/> = | ||
| − | < | + | <references /> |
| + | [[Category:Micro_Hydro]] | ||
| + | [[Category:Hydro]] | ||
| + | [[Category:Rwanda]] | ||
[[Category:Financing_and_Funding]] | [[Category:Financing_and_Funding]] | ||
Latest revision as of 11:13, 30 September 2015
Overview
Micro-Hydro Power (MHP) projects come along with a big variety of costs. Planning and developing a site brings a number of country, probably regional specific costs. Similar to that are costs for operation and maintenance. All different cost categories play a role for individual projects, while big difference between countries due to different framework condition might occur. A clear cost analysis upfront is highly recommended.
Costs
Cost Factors are Eventually:
- a locations feasibility check by respective personal
- land/water ownership/usage
- civil construction (canal, wear, intake, pipes, powerhouse)
- electro-mechanical equipment (turbine, generator, load controller)
- power grid (evtl. transformers, powerlines, house-cabeling, load limiters, meter installation, ...)
- operation & maintenance (collecting tariffs, running and maintaining the assets)
Some remarks regarding costs:
- Land & water requirements are mostly small. But there may be interference with existing schemes (irrigation) or legal issues to be considered.
- Order to delivery of electro-mechanical equipment may take half a year. Ensure to order in time.
- Costs for power lines and household connections often require a substantial amount from the overall budged.
- Any mhp scheme supplying a group of households has to install fixed procedures to cover operation & maintenance.
- This includes the collection of tariffs from each user.
Example: Micro-Hydro Power (MHP) Costs in Rwanda
- A special chapter about the management costs was developed, too.