=== Definition of Pico hydropower  ===
+
[[Portal:Hydro|►Back to Hydro Portal]]<br/>
 
+
= Introduction<br/> =
Turbines '''smaller than 10 kW''' are usually called "pico". Pico hydro rarely is fed into a power grid, but mostly serves a village or a workshop with electricity. As there are varying definitions of the power range of of "micro" and "pico", it is advantageous to specify each project's power output in kW. <br>
+
'''Pico hydro power''': Turbines '''smaller than 10 kW''' are usually called "pico". Pico hydro power is rarely fed into a power grid, but in most cases electricity is delivered to a village or a workshop. As there are varying definitions of the power range of of "micro" and "pico", it is advantageous to specify each project's power output in kW.<br/>
 
+
<br/>
=== Concept of Pico hydropower  ===
+
= Concept<br/> =
 
+
Pico hydropower is the only form of small renewable energy production which works continuously without battery storage. Where applicable it is the most cost efficient solution to supply electrical energy. Pico turbines can provide power '''for small clusters or even single households'''<br/>
Pico hydropower is the only form of small renewable energy production which works continuously without battery storage. Where applicable it is the most cost efficient solution to supply electrical energy. Pico turbines can provide power '''for small clusters or even single households'''  
+
'''Individual hydropower supply''' cuts out the efforts of organising a community. Identifying, planning and managing takes a higher proportion of the whole installation efforts as smaller a sites becomes. For less consumers served, specialists have similar efforts in accessing sites. On the other hand small installation are more likely to be "'''do it your self'''".<br/>With guidance by info materials and advise from a local shop consumers could be enabled to install their own pico turbine. If pico hydropower can become an "'''over the counter'''" product it meets a immense demand.<br/>One example may be the north of Laos where cheap Chinese pico-turbines flooded the country in ten-thousands or more.<br/><br/><u>Requirements:</u>
 
+
*suitable locations
'''Individual hydropower supply''' cuts out the efforts of organising a community. Identifying, planning and managing takes a higher proportion of the whole installation efforts as smaller a sites becomes. For less consumers&nbsp; served, specialists have similar efforts in accessing&nbsp; sites. On the other hand small installation are more likely to be "'''do it your self'''".<br>With guidance by info materials and advise from a local shop consumers could be enabled to install their own pico turbine. If pico hydropower can become an "'''over the counter'''" product it meets a immense demand. <br>One example may be the north of Laos where cheap Chinese pico-turbines flooded the country in ten-thousands or more.<br><br><u>Requirements:</u>  
 
 
 
*suitable locations  
 
 
*accessibility of affordable equipment (turbines) and installation know how
 
*accessibility of affordable equipment (turbines) and installation know how
 +
<br/>
 +
Electricity has a high value so working systems will spread quickly.<br/>In many countries self-made solutions can be found, whereby a wooden water wheel is coupled with a car-alternator to produce electricity. Professional solutions increase efficiency reliability and safety.
 +
<br/>
 +
<br/>
 +
=== Pico Hydro Turbines<br/> ===
  
Electricity has a high value so working systems will spread quickly.<br>In many countries self-made solutions can be found, whereby a wooden water wheel is coupled with a car-alternator to produce electricity. Professional solutions increase efficiency reliability and safety.<br>
+
==== Principles of Turbines for high, medium and low head conditions<br/> ====
  
=== Pico Hydro Turbines  ===
+
{| cellspacing="1" cellpadding="1" border="0" style="width: 721px; height: 350px" class="FCK__ShowTableBorders"
 
 
==== Principles of Turbines for high, medium and low head conditions  ====
 
 
 
{| class="FCK__ShowTableBorders" style="width: 721px; height: 350px" cellspacing="1" cellpadding="1" border="0"
 
 
|-
 
|-
| [[Image:Pico-Turbines.jpg|thumb|left|319x318px]]  
+
| [[File:Pico-Turbines.jpg|thumb|left|180px|Pico-turbine types]]
|  
+
|
Each type of turbine has its own features.  
+
Each type of turbine has its own features.
 
+
The main characteristic it's the turbines suitability for different heads and different amounts of water (see picture left).
The main characteristic it's the turbines suitability for different heads and different amounts of water (see picture left).  
+
In general a Crossflow turbine has the wides application range and is very tolerant against debris in water.
 
+
"Self made" Pico turbines usually are waterwheels or propeller turbines. The concept of pressurised pipes over high heads seems not to be common sense. One reason may be that channeling water towards a deep drop requires abstraction of existing landscape. It cannot be seen from a single standpoint. Informative materials may help to raise awareness for such potentials.
In general a Crossflow turbine has the wides application range and is very tolerant against debris in water.  
+
<br/>
 
 
"Self made" Pico turbines usually are waterwheels or propeller turbines. The concept of pressurised pipes over high heads seems not to be common sense. One reason may be that channeling water towards a deep drop requires abstraction of existing landscape. It cannot be seen from a single standpoint. Informative materials may help to raise awareness for such potentials.  
 
 
 
<br>
 
 
 
 
|}
 
|}
 +
<br/>
 +
<br/>
 +
==== Experiences with Certain Pico Turbines<br/> ====
  
==== Experiences with certain pico turbines  ====
+
{| cellspacing="1" cellpadding="1" border="0" style="width: 721px; height: 549px" class="FCK__ShowTableBorders"
 
 
{| class="FCK__ShowTableBorders" style="width: 721px; height: 549px" cellspacing="1" cellpadding="1" border="0"
 
 
|-
 
|-
|  
+
|
'''TP100''' was developed 2008 by PT.Entec-Indonesia, to be produced in small workshops<br>
+
'''TP100''' <br/>
 +
TP100 was developed 2008 by PT.Entec-Indonesia, to be produced in small workshops<br/>
  
{| class="FCK__ShowTableBorders" cellspacing="1" cellpadding="1" width="200" border="0"
+
{| cellspacing="1" cellpadding="1" border="1" style="width: 200px" class="FCK__ShowTableBorders"
 
|-
 
|-
| Power  
+
| Power
| [http://energypedia.info/images/1/1c/Tp100_application-range.jpg 500 -2000 W]
+
| [[:File:Tp100 application-range.jpg|500 -2000 W]]
 
|-
 
|-
| Site  
+
| Site
| 8 - 40 m @ 10 - 25 l/s<br>
+
| 8 - 40 m @ 10 - 25 l/s
 
|-
 
|-
| Cost<br>
+
| Cost
| ~ 700 USD<br>
+
| ~ 700 USD
 
|}
 
|}
 
+
*Suitable for 1 - 50 household installations<br/>
Suitable for 1 - 50 household installations<br>
+
*Additional cost*: 500 - 2000 USD<br/>
 
+
*<sup>*</sup>depending on length of transmission cable
Additional&nbsp; cost*: 500 - 2000 USD<br>
+
Factsheets on site installations in Indonesia: [[:File:Mini_Hydro_Power_Project_in_Salulombe,Indonesia.pdf|Salulombe]]and[[:File:Mini_Hydro_Power_Project_in_Garumpar,_Indonesia.pdf|Garumpar]]<br/>
 
+
|
<sup>*</sup>depending on&nbsp; length of transmission cable<br>
+
[[File:Infobox Tp100.jpg|thumb|right|180px|Infobox Tp100]]<br/>
 
 
Factsheets on site installations in Indonesia:  
 
 
 
[http://energypedia.info/index.php/File:Factsheet_Tp100_Salulombe_small.pdf Salulombe], [http://energypedia.info/index.php/File:Factsheet_Tp100_Garumpar_small.pdf Garumpar]
 
 
 
|  
 
[[Image:Infobox Tp100.jpg|thumb|right|245x246px]]
 
 
 
 
|-
 
|-
|  
+
|
'''TC60 (100 W)'''<br>
+
'''TC60 (100 W)'''<br/>
 
+
CIT in Bandung, Indonesia developed the "TC60" inspired by Vietnamese/Chinese low cost Open Flume turbine (OF turbine) design. Sales started at the beginning of 2007. With a price less than 300 USD makes TC60 an option for private energy supply for single households. It produces 100 W at site specifications of only 3 m head and a flow < 10 l/s. Total installation cost depend on cable length from turbine to house. (50 USD/ 100 m).<br/>
CIT in Bandung, Indonesia developed the "TC60" inspired by Vietnamese/Chinese low cost Open Flume turbine (OF turbine) design. Sales started at the beginning of 2007. With a price less than 300 USD makes TC60 an option for private energy supply for single households. It produces 100 W at site specifications of only 3 m head and a flow &lt; 10 l/s. Total installation cost depend on cable length from turbine to house. (50 USD/ 100 m).  
 
  
{| class="FCK__ShowTableBorders" cellspacing="1" cellpadding="1" width="200" border="0"
+
{| cellspacing="1" cellpadding="1" border="1" style="width: 200px" class="FCK__ShowTableBorders"
 
|-
 
|-
| Power  
+
| Power
 
| 100 W
 
| 100 W
 
|-
 
|-
| Site  
+
| Site
 
| 3m @ 8 l/s
 
| 3m @ 8 l/s
 
|-
 
|-
| Cost  
+
| Cost
 
| 250 USD
 
| 250 USD
 
|}
 
|}
 
+
*Suitable for 1 - 5 households (lighting)<br/>
Suitable for 1 - 5 households (lighting)<br>
+
*Additional cost*: 50 - 200 USD
 
+
<sup>*</sup>depending on length of transmission cable<br/>
Additional&nbsp; cost*: 50 - 200 USD<br><sup>*</sup>depending on&nbsp; length of transmission cable <br><br>
+
| [[File:Infobox TC60.jpg|thumb|right|180px|Infobox TC60]]
 
 
| [[Image:Infobox TC60.jpg|thumb|right|245x245px]]
 
|-
 
| <br>
 
| <br>
 
 
|}
 
|}
 
+
<br/>
<br>
+
<br/>
 
+
=== Chances and Challenges<br/> ===
=== Chances and challenges<br> ===
+
<u>'''Advantages:'''</u><br/>
 
+
*Cheapest technical solution for independent power supply.
'''Advantages'''<br>
+
*Clean, sustain-/ renewable energy resource.
 
+
*Reliable => long lifetime as it is based upon robust mechanical techniques.
*Cheapest technical solution for independent power supply.  
+
*Minimal running and follow up costs (unlike batteries at PV systems).
*Clean, sustain-/ renewable energy resource.  
 
*Reliable =&gt; long lifetime as it is based upon robust mechanical techniques.  
 
*Minimal running and follow up costs (unlike batteries at PV systems).  
 
 
*Small maintenance efforts, which are easy to follow.
 
*Small maintenance efforts, which are easy to follow.
 +
<u><br/>'''Disadvantages:'''</u><br/>
 +
*Site specific power output => pre-feasibility check required.
 +
*Site specific installation => basic hydro know-how required.
 +
*All cost are investment cost => upfront.
 +
*Mostly shared connections => require community organised operation, management and use of water resources.
 +
*Difficult access of clients => requires hubs and/or supply structure.
 +
<br/>
 +
<br/>
 +
=== Capacity ===
 +
Power output is limited by local conditions of height and amount of water available. Turbines are chosen by site conditions.<br/>The following is an example for one specific turbine designed in Indonesia.
 +
<br/>
 +
<u>Explanation:</u>[[File:Tp100 application-range example.jpg|thumb|right|500px|Tp100 application-range example|alt=Tp100 application-range example.jpg]]<br/>The colored lines indicate the power output at certain height/flow situations. The red horizontal line such turbine is technically not feasible, the blue "2 kW" line indicates a tech. maximum (for this specific turbine). The dotted lines separate three areas wherein turbines have certain sizes (30, 60 and 100 mm wide).<br/>Example: at a site with 15 m height difference and a flow of 15 l/s the turbine can produce 1.5 kW (it will have a width of 60 mm). If on the same site (15 m) 25 l/s flow, power output will be 1.8 kW.<br/>
 +
<br/>
 +
<u>Remark: </u><br/>to produce the same electric power by [[Photovoltaic (PV)|photovoltaic]] you require about 50 m<sup>2</sup> PV-panels (and min. 20 batteries).
 +
<br/>
 +
<br/>
 +
= Pico Hydro Materials<br/> =
  
<br>'''Disadvantages'''<br>
+
*'''Pump as Turbine'''
 
+
it is possible to use water pumps "backwards" as turbines. Advantages is a wide availability also from spare parts.
*Site specific power output =&gt; pre-feasibility check required.
+
Manual how to plan a site by using a [[:File:Pump as Turbine (PaT) Manual.doc|Pump as Turbine]] (PaT)<br/>
*Site specific installation =&gt; basic hydro know-how required.
+
<br/>
*All cost are investment cost =&gt; upfront.
+
*'''A Buyers Guide'''
*Mostly shared connections =&gt; require community organised operation, management and use of water resources.
+
Canadian brochure of 56 pages. Containing general information about: planning, components, costs, examples and turbine producers of hydropower installations ranging from 200 W - 15 kW.  
*Difficult access of clients =&gt; requires hubs and/or supply structure.<br>
+
"[[:File:Micro Hydropower System - A Buyer's Guide.pdf|A Buyers Guide]]" a nice overview, easy understandable.
 
+
<br/>
=== Capacity  ===
+
*'''Pico hydropower attempts''', MHPP, Indonesia, 2007-08
 
+
A consolidation of the Pico hydropower efforts in Indonesia during 2007-08. Especially the results on a feasibility research on Family hydro units. An approach to spread turbine technology for single households or very small clusters of users.<br/>
<br>Power output is limited by local conditions of height and amount of water available. Turbines are chosen by site conditions.<br>The following is an example for one specific turbine designed in Indonesia.<br>
+
► [[:File:MHPP's Pico Component 2007-08.pdf|MHPP's Pico Component 2007-08 (pdf]])<br/>
 
+
<br/>
<u>Explanation:</u>[[Image:Tp100 application-range example.jpg|right|507x291px|Tp100 application-range example.jpg]]<br>The colored lines indicate the power output at certain height/flow situations. The red horizontal line such turbine is technically not feasible, the blue "2 kW" line indicates a tech. maximum (for this specific turbine). The dotted lines separate three areas wherein turbines have certain sizes (30, 60 and 100 mm wide).<br>Example: at a site with 15 m height difference and a flow of 15 l/s the turbine can produce 1.5 kW (it will have a width of 60 mm). If on the same site (15 m) 25 l/s flow, power output will be 1.8 kW.<br>
+
*'[[Pocket-Hydro|Pocket Hydro]] ''– ''''''a mini power plant for decentralized electric power'''<br/>
 
+
Ongoing project with the '''aim''' to provide affordable electric lighting through the use of local water energy in remote rural areas.<br/>
<u>Remark: </u><br>to produce the same electric power by [[Photovoltaics|photovoltaic]] you require about 50 m<sup>2</sup> PV-panels (and min. 20 batteries).
+
<br/>
 
+
<br/>
<br>
+
= Further Information<br/> =
 
 
=== Pico Hydro Materials  ===
 
 
 
'''Pump as Turbine'''<br>
 
 
 
it is possible to use water pumps "backwards" as turbines. Advantages is a wide availability also from spare parts. <br>
 
 
 
=&gt; Manual how to plan a site by using a [http://energypedia.info/images/d/d8/PaT-Manual_1.2.doc Pump as Turbine] (PaT)<br>  
 
 
 
'''A Buyers Guide'''  
 
 
 
Canadian brochure of 56 pages. Containing general information about: planning, components, costs, examples and turbine producers of hydropower installations ranging from 200 W - 15 kW. "[http://energypedia.info/images/d/d1/MicroHydroGuide.pdf A Buyers Guide]" a nice overview, easy understandable.<br>  
 
 
 
'''Pico hydropower attempts''', MHPP, Indonesia, 2007-08  
 
  
A consolidation of the Pico hydropower efforts in Indonesia during 2007-08. Especially the results on a feasibility research on Family hydro units. An approach to spread turbine technology for single households or very small clusters of users. [http://energypedia.info/images/d/d7/MHPP%27s_Pico_Component_2007-08.pdf MHPP's Pico Component 2007-08.pdf]
+
*[[Portal:Hydro|Hydro Portal on energypedia]]<br/>
 +
*[[Hydro_Power_Basics|Hydro Power Basics]]<br/>
 +
<br/>
 +
= References<br/> =
 +
<references /><br/>
  
[[Category:Hydro|<br>]]
+
[[Category:Hydro]]
 +
[[Category:Micro-Hydro/Pico-Hydro]]

Latest revision as of 14:54, 22 January 2016

►Back to Hydro Portal

Introduction

Pico hydro power: Turbines smaller than 10 kW are usually called "pico". Pico hydro power is rarely fed into a power grid, but in most cases electricity is delivered to a village or a workshop. As there are varying definitions of the power range of of "micro" and "pico", it is advantageous to specify each project's power output in kW.

Concept

Pico hydropower is the only form of small renewable energy production which works continuously without battery storage. Where applicable it is the most cost efficient solution to supply electrical energy. Pico turbines can provide power for small clusters or even single households
Individual hydropower supply cuts out the efforts of organising a community. Identifying, planning and managing takes a higher proportion of the whole installation efforts as smaller a sites becomes. For less consumers served, specialists have similar efforts in accessing sites. On the other hand small installation are more likely to be "do it your self".
With guidance by info materials and advise from a local shop consumers could be enabled to install their own pico turbine. If pico hydropower can become an "over the counter" product it meets a immense demand.
One example may be the north of Laos where cheap Chinese pico-turbines flooded the country in ten-thousands or more.

Requirements:

  • suitable locations
  • accessibility of affordable equipment (turbines) and installation know how


Electricity has a high value so working systems will spread quickly.
In many countries self-made solutions can be found, whereby a wooden water wheel is coupled with a car-alternator to produce electricity. Professional solutions increase efficiency reliability and safety.

Pico Hydro Turbines

Principles of Turbines for high, medium and low head conditions

Pico-turbine types

Each type of turbine has its own features. The main characteristic it's the turbines suitability for different heads and different amounts of water (see picture left). In general a Crossflow turbine has the wides application range and is very tolerant against debris in water. "Self made" Pico turbines usually are waterwheels or propeller turbines. The concept of pressurised pipes over high heads seems not to be common sense. One reason may be that channeling water towards a deep drop requires abstraction of existing landscape. It cannot be seen from a single standpoint. Informative materials may help to raise awareness for such potentials.



Experiences with Certain Pico Turbines

TP100
TP100 was developed 2008 by PT.Entec-Indonesia, to be produced in small workshops

Power 500 -2000 W
Site 8 - 40 m @ 10 - 25 l/s
Cost ~ 700 USD
  • Suitable for 1 - 50 household installations
  • Additional cost*: 500 - 2000 USD
  • *depending on length of transmission cable

► Factsheets on site installations in Indonesia: SalulombeandGarumpar

Infobox Tp100

TC60 (100 W)
CIT in Bandung, Indonesia developed the "TC60" inspired by Vietnamese/Chinese low cost Open Flume turbine (OF turbine) design. Sales started at the beginning of 2007. With a price less than 300 USD makes TC60 an option for private energy supply for single households. It produces 100 W at site specifications of only 3 m head and a flow < 10 l/s. Total installation cost depend on cable length from turbine to house. (50 USD/ 100 m).

Power 100 W
Site 3m @ 8 l/s
Cost 250 USD
  • Suitable for 1 - 5 households (lighting)
  • Additional cost*: 50 - 200 USD

*depending on length of transmission cable

Infobox TC60



Chances and Challenges

Advantages:

  • Cheapest technical solution for independent power supply.
  • Clean, sustain-/ renewable energy resource.
  • Reliable => long lifetime as it is based upon robust mechanical techniques.
  • Minimal running and follow up costs (unlike batteries at PV systems).
  • Small maintenance efforts, which are easy to follow.


Disadvantages:

  • Site specific power output => pre-feasibility check required.
  • Site specific installation => basic hydro know-how required.
  • All cost are investment cost => upfront.
  • Mostly shared connections => require community organised operation, management and use of water resources.
  • Difficult access of clients => requires hubs and/or supply structure.



Capacity

Power output is limited by local conditions of height and amount of water available. Turbines are chosen by site conditions.
The following is an example for one specific turbine designed in Indonesia.

Explanation:

Tp100 application-range example.jpg
Tp100 application-range example


The colored lines indicate the power output at certain height/flow situations. The red horizontal line such turbine is technically not feasible, the blue "2 kW" line indicates a tech. maximum (for this specific turbine). The dotted lines separate three areas wherein turbines have certain sizes (30, 60 and 100 mm wide).
Example: at a site with 15 m height difference and a flow of 15 l/s the turbine can produce 1.5 kW (it will have a width of 60 mm). If on the same site (15 m) 25 l/s flow, power output will be 1.8 kW.


Remark:
to produce the same electric power by photovoltaic you require about 50 m2 PV-panels (and min. 20 batteries).

Pico Hydro Materials

  • Pump as Turbine

it is possible to use water pumps "backwards" as turbines. Advantages is a wide availability also from spare parts. ► Manual how to plan a site by using a Pump as Turbine (PaT)

  • A Buyers Guide

Canadian brochure of 56 pages. Containing general information about: planning, components, costs, examples and turbine producers of hydropower installations ranging from 200 W - 15 kW. ► "A Buyers Guide" a nice overview, easy understandable.

  • Pico hydropower attempts, MHPP, Indonesia, 2007-08

A consolidation of the Pico hydropower efforts in Indonesia during 2007-08. Especially the results on a feasibility research on Family hydro units. An approach to spread turbine technology for single households or very small clusters of users.
MHPP's Pico Component 2007-08 (pdf)

  • 'Pocket Hydro – 'a mini power plant for decentralized electric power

Ongoing project with the aim to provide affordable electric lighting through the use of local water energy in remote rural areas.